Question
Calculate the following: A) Construction project budget calls for the following expenditures: B) Refer to the definitions of each term, calculate these values for the
- Calculate the following:
A) Construction project budget calls for the following expenditures:
B) Refer to the definitions of each term, calculate these values for the above project, and show your work:
- Budget at completion (BAC)
- Planned value (PV) as of May 1
- Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
- Schedule Variance (SV) as of May 1.
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that past variances are not expected to continue
- Estimated Final Project Cost (EAC)
* Note: Make sure to include ALL tasks that were completed as of May 1st.
C) Show your work with formulas
- Answer the following questions:
1) Is the project on schedule as of May 1? What indicator did you use? Explain. 2) Is the project achieving more than predicted for the money as of May 1? What indicator did you use? Explain. 3) Is the project on budget as of May 1? What indicator did you use? Explain.
*Note: All cells that require input are highlighted in blue in the worksheet.
Construction Project Earned-Value Analysis | ||||||||
Project Budget | ||||||||
Task | Date | Budgeted Amount | ||||||
Build forms | 1-Apr | $10,000 | ||||||
Pour foundation | 1-Apr | $50,000 | ||||||
1-May | $100,000 | |||||||
Frame walls | 1-May | $30,000 | ||||||
1-Jun | $30,000 | |||||||
Remaining tasks | July 1 and beyond | $500,000 | ||||||
Budget at Completion (BAC) | ||||||||
Results as of May 1 | ||||||||
Foundation completed % | 66.67% | |||||||
Everything else is on schedule. | ||||||||
Actual Cost | $160,000 | |||||||
Previous cost variances will not affect future costs | ||||||||
Calculate as of May 1st | ||||||||
PV | ||||||||
EV | ||||||||
AC | ||||||||
SV | ||||||||
CV | ||||||||
SPI | ||||||||
CPI | ||||||||
ETC | ||||||||
EAC | ||||||||
Answer the following questions | ||||||||
1) Is the project on schedule as of May 1? What indicator did you use? Explain. | ||||||||
2) Is the project achieving more than predicted for the money as of May 1? What indicator did you use? Explain. | ||||||||
3) Is the project on budget as of May 1? What indicator did you use? Explain. | ||||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started