Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Calculate the following: A) Construction project budget calls for the following expenditures: B) Refer to the definitions of each term, calculate these values for the

  • Calculate the following:

A) Construction project budget calls for the following expenditures:

B) Refer to the definitions of each term, calculate these values for the above project, and show your work:

  1. Budget at completion (BAC)
  2. Planned value (PV) as of May 1
  3. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  4. Schedule Variance (SV) as of May 1.
  5. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  6. Schedule performance index (SPI)
  7. Cost performance index (CPI)
  8. Estimate to complete (ETC), assuming that past variances are not expected to continue
  9. Estimated Final Project Cost (EAC)

* Note: Make sure to include ALL tasks that were completed as of May 1st.

C) Show your work with formulas

  • Answer the following questions:

1) Is the project on schedule as of May 1? What indicator did you use? Explain. 2) Is the project achieving more than predicted for the money as of May 1? What indicator did you use? Explain. 3) Is the project on budget as of May 1? What indicator did you use? Explain.

*Note: All cells that require input are highlighted in blue in the worksheet.

Construction Project Earned-Value Analysis
Project Budget
Task Date Budgeted Amount
Build forms 1-Apr $10,000
Pour foundation 1-Apr $50,000
1-May $100,000
Frame walls 1-May $30,000
1-Jun $30,000
Remaining tasks July 1 and beyond $500,000
Budget at Completion (BAC)
Results as of May 1
Foundation completed % 66.67%
Everything else is on schedule.
Actual Cost $160,000
Previous cost variances will not affect future costs
Calculate as of May 1st
PV
EV
AC
SV
CV
SPI
CPI
ETC
EAC
Answer the following questions
1) Is the project on schedule as of May 1? What indicator did you use? Explain.
2) Is the project achieving more than predicted for the money as of May 1? What indicator did you use? Explain.
3) Is the project on budget as of May 1? What indicator did you use? Explain.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Mastering Auditing Essentials A Comprehensive Guide To Learn Auditing Essentials

Authors: Cybellium Ltd, Kris Hermans

1st Edition

B0CHL7H261, 979-8861235617

More Books

Students also viewed these Accounting questions

Question

Does it have at least one-inch margins?

Answered: 1 week ago

Question

Does it highlight your accomplishments rather than your duties?

Answered: 1 week ago