Calculate the fully loaded cost of labor for the project team using the following data. What are the costs for the individual project team members?

Calculate the fully loaded cost of labor for the project team using the following data.

What are the costs for the individual project team members? What is the fully loaded cost of labor?

image text in transcribed

image text in transcribed

Fully Loaded Labor Cost Hours Overhead Personal Hourly Name Needed Charge Time Rate Rate Sandy 60 1.35 1.12 $18/hr Chuck 80 1.75 1.12 $31/hr Fully Loaded Labor Cost Hours Overhead Personal Hourly Name Needed Charge Time Rate Rate Bob 1.35 -O $9/hr Penny 1.75 1.12 $30/hr Total Fully Loaded Labor Cost = 80 40

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Finance Applications and Theory

Authors: Marcia Cornett

4th edition

1259691411, 978-1259691416

More Books

Students also viewed these Finance questions

Question

Discuss the relative growth rates of x!,2x,and x2.

Answered: 1 week ago