Calculate the On Hand balance for Week 6 in the MRP work sheet below given the following information: On Hand = 225 Lead time =
Calculate the On Hand balance for Week 6 in the MRP work sheet below given the following information: On Hand = 225 Lead time = 3 weeks Lot Size = 75 Week 1 2 3 4 5 6 7 8 Gross Requirements 75 50 100 200 100 50 225 100 Schedule Receipts On Hand 225 Planned Order Release Group of answer choices 50 0 75 25