Calculate the Payback for Project A. PROJECT A -2000 500 600 700 800 PROJECT B -2000 950 850 400 300 Select an answer and submit.
Calculate the Payback for Project A. PROJECT A -2000 500 600 700 800 PROJECT B -2000 950 850 400 300 Select an answer and submit. For keyboard navigation, use the up/down arrow keys to select an answer. 3 years b 3.25 years 3.5 years d 4 years e 4.25 years