Question
1 Approved Answer
Calculate the three-point estimates (weighted averages) for the following activity durations: Optimistic (O) Most Likely (ML) Pessimistic (P) Solution Activity 1 5 8 15 Activity
Calculate the three-point estimates (weighted averages) for the following activity durations: Optimistic (O) Most Likely (ML) Pessimistic (P) Solution Activity 1 5 8 15 Activity 2 6 15 21 Activity 3 1 3 6 Activity 4 20 22 23 Activity 5 12 17 30 Activity 6 43 45 49 Activity 7 73 73 73 Activity 8 25 28 38