calculate the values for week 4 calculate the values for week 4 planned value, actual cost , earned value , sv, cv, spi , cpi

calculate the values for week 4 image text in transcribed
calculate the values for week 4 planned value, actual cost , earned value , sv, cv, spi , cpi
what information do you want more? its exam question with full detail
activities are given
STATUS REPORT WEEK 4 ChicoWeb Period: 22/12-28/12 SR-241-01-SS Schedule Actual start: 01/12 Planned start: Planned end: 01/12 30/12 Actual end: Budget Planned budget: $13.320,00 Actual total cost: $? Plan week 4 ID Activity Planned Planned Planned Planned Planned T 14 24.1 Monitor & control week 4 Pan system tests $ 27000100 S160100 2.5.1 Install system $ 150,00 24/12 24/12 23/12 25/12 26/12 25/12 2000 100% 26/12 2.5.2 Verify and accept project Prepare training material 32 Rere trainine Activities realized during week 2 Activity Responsible ID Rese Actual cost Actual start Actual and completed Effort spent person-hours) 10 22/12 26/12 25% 1.4 2.4.1 Monitor & control Week 4 Plan system tests Leonardo Karen Mauricio SOX $500.00 160,00 $240.00 $150,00 $40,00 - 2.4.2 Execute system tests 2.5.1 install system Karen Karen Karen 2 0 23/12 24/12 - - - 0% 2.5.2 3.1 Verify and accept project Prepare training material Jolo $200,00 25/12 3.2 Realine training Jodo Earned Value Management Week Planned value Actual cost Earned Value SV Week 1 $ 3.280,00 $ 3.280,00 $-320.00 $0.00 0.91 $3.600.00 $6,600,00 Week 2 $6,600.00 $ 6,600,00 Sood SO 10 Week 3 $ 10.200,00 $11.600,00 $10.200,00 $0.00 $-1.400,00 Week 4 $ 13.320,00 Issues: All employees who worked on 25/12 are receiving overtime payment. 2. The intern Karen was quite lost on running tests. She did not even know how to begin. Therefore, Mauricio helped here on the night of 22/12 to plan at least some tests. 3. When Karen arrived at the pizzeria on December, 24 to install the system, the pizzeria was dosed due to Christmas vacations 4. Leonardo tried to locate the owner of the pizzeria to solve the problem, but the owner was away on vacation 5. On December, 25/26, John simply did not appear for work. Calling Mouse he agreed to come and prepared the training 6. The Christmas party was a great success - everyone stayed until late. STATUS REPORT WEEK 4 ChicoWeb Period: 22/12-28/12 SR-241-01-SS Schedule Actual start: 01/12 Planned start: Planned end: 01/12 30/12 Actual end: Budget Planned budget: $13.320,00 Actual total cost: $? Plan week 4 ID Activity Planned Planned Planned Planned Planned T 14 24.1 Monitor & control week 4 Pan system tests $ 27000100 S160100 2.5.1 Install system $ 150,00 24/12 24/12 23/12 25/12 26/12 25/12 2000 100% 26/12 2.5.2 Verify and accept project Prepare training material 32 Rere trainine Activities realized during week 2 Activity Responsible ID Rese Actual cost Actual start Actual and completed Effort spent person-hours) 10 22/12 26/12 25% 1.4 2.4.1 Monitor & control Week 4 Plan system tests Leonardo Karen Mauricio SOX $500.00 160,00 $240.00 $150,00 $40,00 - 2.4.2 Execute system tests 2.5.1 install system Karen Karen Karen 2 0 23/12 24/12 - - - 0% 2.5.2 3.1 Verify and accept project Prepare training material Jolo $200,00 25/12 3.2 Realine training Jodo Earned Value Management Week Planned value Actual cost Earned Value SV Week 1 $ 3.280,00 $ 3.280,00 $-320.00 $0.00 0.91 $3.600.00 $6,600,00 Week 2 $6,600.00 $ 6,600,00 Sood SO 10 Week 3 $ 10.200,00 $11.600,00 $10.200,00 $0.00 $-1.400,00 Week 4 $ 13.320,00 Issues: All employees who worked on 25/12 are receiving overtime payment. 2. The intern Karen was quite lost on running tests. She did not even know how to begin. Therefore, Mauricio helped here on the night of 22/12 to plan at least some tests. 3. When Karen arrived at the pizzeria on December, 24 to install the system, the pizzeria was dosed due to Christmas vacations 4. Leonardo tried to locate the owner of the pizzeria to solve the problem, but the owner was away on vacation 5. On December, 25/26, John simply did not appear for work. Calling Mouse he agreed to come and prepared the training 6. The Christmas party was a great success - everyone stayed until late

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Financial Management

Authors: R. Charles Moyer, William J. Kretlow, James R. Mcguigan

7th Edition

0538877766, 9780538877763

More Books

Students also viewed these Finance questions

Question

What do you see as your biggest strength/weakness?

Answered: 1 week ago

Question

Draw a picture consisting parts of monocot leaf

Answered: 1 week ago