Calculate the work done and the Earned Value at the end of one week in the following situation: Time estimated to complete project: 8 0

Calculate the work done and the Earned Value at the end of one week in the following situation:
Time estimated to complete project: 80 hours
Duration of project: 2 weeks
Planned value: 40 hours per week
Actual time required over the first week: 30
Actual time required to finish the project: 30
Work done = Blank 1%
Earned value = Blank 2 hours
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Facilities Planning

Authors: James A. Tompkins, John A. White, Yavuz A. Bozer, J. M. A. Tanchoco

4th Edition

0470444045, 978-0470444047

More Books

Students also viewed these General Management questions