Question
Calculate total sales mix variance, Direct Materials Variance Price, Direct Materials Variance Efficiency, Dircet Labor Variance Rate & Efficiency, Variable overhead variance spending, and Selling
Calculate total sales mix variance, Direct Materials Variance Price, Direct Materials Variance Efficiency, Dircet Labor Variance Rate & Efficiency, Variable overhead variance spending, and Selling and General Admin Variance.
Scooter's Inc Summary of Standard Costs | |||
Summary of Standard Costs | Deluxe | Beginner | |
Assembly kit per scooter | $ 400 | $ 200 | |
Direct labor hours per scooter | 3 | 1 | |
Direct labor rate per hour | $ 25 | $ 15 | |
Variable overhead rate per scooter | $ 35 | $ 35 | |
| |||
Sales Price | |||
|
| ||
| 2017 | 2018 | |
Deluxe | $ 900 | $ 900 | |
Beginner | $ 350 | $ 350 | |
| |||
Sales Mix Percent | |||
| 2017 | 2018 | |
Deluxe | 80% | 50% | |
Beginner | 20% | 50% | |
| |||
Total Assembled & Sold | 6,800 | 6,800 | |
| |||
Scooter's Inc | |||
Summary of Actual Costs | |||
| |||
Deluxe | 2017 | 2018 | |
Assembly kits: | Used | 5,440 | 3,425 |
| Price per kit | $ 400 | $ 500 |
Direct labor hours |
| 16,320 | 10,275 |
Direct labor rate per hour |
| $ 25 | $ 27 |
Variable overhead per scooter |
| $ 35 | $ 38 |
| |||
Beginner | 2017 | 2018 | |
Assembly kits: | Used | 1,360 | 3,460 |
| Price per kit | $ 200 | $ 175 |
Direct labor hours |
| 1,360 | 3,460 |
Direct labor rate per hour |
| $ 15 | $ 20 |
Variable overhead per scooter |
| $ 35 | $ 41 |
Director salaries |
| $ 400,000 | $ 275,000 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started