Calculating Indirect Rates Cost ElementCostSubtotalRate Direct Labor Base $15,500,000.00 Overhead Expense $8,000,000.00 Burdened Labor Subtototal $ Other Direct Costs Subcontracts $3,500,000.00 Materials $3,250,000.00 Travel $35,000.00
Calculating Indirect Rates
Cost ElementCostSubtotalRate
Direct Labor Base $15,500,000.00
Overhead Expense $8,000,000.00
Burdened Labor Subtototal $
Other Direct Costs
Subcontracts $3,500,000.00
Materials $3,250,000.00
Travel $35,000.00
Special Tooling $875,000.00
ODC Subtotal $
G&A Cost Base $
G&A Expense $5,500,000.00
Total Costs $
Overhead Rate%
G&A Rate%
Profit $ 10%
Contract Total $
(1) In the blank provided enter the Burdened Labor Subtotal.Be sure to include the commas and decimal values (to two places for example for $50 enter 50.00) as well.You DO NOT need to include the $ sign.The total Burdened Labor Subtotal is $
(2) The total value for the other direct costs in this exercise is (select correct answer)
cannot be determined without knowing the value of the direct costs
$ 4,160,000.00
$ 7,660,000.00
$ 31,160,000.00
(3) Which of the following explains how to obtain the value for total costs?
All costs except overhead and G&A make up the total costs.The total costs for this exercise would be $ 23,160,000.00.
All direct costs, overhead and G&A are added together for a total cost amount of $36,660,000.00
Direct costs, overhead expense and other direct costs are added together for a total of $ 31,160,000.00.
The total cost is the sum of the direct and indirect costs as well as the G&A cost base.The total cost is $62,320,000.00
(4) How would you find the G&A rate for this exercise?
Divide the G&A cost base by the G&A Expense using the following formula Cost Base/Expense Pool
The G&A rate for this exercise is found by dividing the G&A expense pool of $5,5000,000 by the G&A cost base.
When calculating the G&A Rate we would exclude the overhead expenses from the cost base.
The G&A rate is found by dividing the direct costs by the indirect costs.
The G&A rate for this exercise is found by dividing the cost base by the total costs
(5) The overhead rate
includes all costs both direct and indirect in the pool.
The overhead rate is calculated based on the comparison of the G&A expenses of $5,500,000.00 and the overhead expense of $ 8,000,000.00.
In this example the overhead rate is calculated by looking at the relationship of the labor base of $ 15,500,000.00and total costs minus the G&A expense.
The overhead rate is the sum of the indirect costs
In this example the overhead rate is calculated by looking at the relationship of the labor base of $ 15,500,000.00and overhead expenses of $8,000,000.
(6) Profit in this example is
10% of the direct costs
10% of the costs minus the G&A expense of $ 5,550,000.00
10% of the total costs
only applied to the direct labor cost plus the other direct costs.
(7) The contract total in this example
will include all direct costs and indirect costs plus profit
will be over $50,000,000.00
will not include G&A expenses
will not include profit
(8) In looking at this worksheet how many indirect cost pools are indicated?
none - in this example all the costs are charged as direct
three- overhead, G&A and other direct costs
one - overhead
two -overhead and G&A
(9) In considering the pricing which of the following is true?
If there were 100 employees and all made the same salary, each would be making $235,000. in salary
Customers have specific requirements for the company to travel to meet the contract requirements
This is probably not a manufacturing company since they have subcontracts
The materials are being provided to the subcontractor
(10) One of the following statements is false.Select the false statement.
The G&A rate is lower than the overhead rate.
Most of the contract cost is related to the direct labor and ovehead
This company is very efficient as they have a low G&A rate
The profit and cost of subcontracts are within $200,000 of each other
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started