Calculation Problem Directions: Show all your work, including formulas used to for full credit for these questions. ( 7 0 points ) The assembly activities

Calculation Problem Directions: Show all your work, including formulas used to for full credit
for these questions.
(70 points)
The assembly activities of a new product must follow the precedence restrictions shown in
the figure below. Task times (in minutes) are shown above each task node and the cycle
time for the production of this product has been set at 40 minutes.
a) List three (3) possible orders in which tasks A to K could be performed on an assembly
line.
b) Find a lower bound on the number of workstations required for an assembly line for
this product.
c) Balance the line using the Ranked Positional Weight Technique.
d) Do you think your solution is optimal? Provide an explanation for your answer.
Note:
Be sure to show details of how you obtained tasks assignments to stations using the
line balancing technique under consideration. Simply stating Station 1 has tasks 1,3
& 5 for example will result in a penalty on your grade.
(20 Points)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Systems Management

Authors: Barbara McNurlin

8th Edition

0132437155, 9780132437158

More Books

Students also viewed these General Management questions

Question

=+b) What are the null and alternative hypotheses?

Answered: 1 week ago

Question

1. Maintain my own perspective and my opinions

Answered: 1 week ago