Calculator The following data relate to direct materials costs for February: Materials cost per yard: standard, $2.00; actual, $2.10 Standard yards per unit: standard, 4.5
Calculator
The following data relate to direct materials costs for February:
Materials cost per yard: standard, $2.00; actual, $2.10
Standard yards per unit: standard, 4.5 yards; actual, 4.75 yards
Units of production: 9,500
Calculate the direct materials quantity variance.
a.$4,750.00 favorable
b.$4,512.50 unfavorable
c.$4,512.50 favorable
d.$4,750.00 unfavorable