can please show how you get the answer? Q1 The chart below shows the Master Production Schedule (MPS) and committed customer orders for a new
can please show how you get the answer?
Q1 The chart below shows the Master Production Schedule (MPS) and committed customer orders for a new MP3 Player you manufacture. Based on this information calculate Available to Promise (ATP.) Discrete ATP Calculation MP3 Player MPS BI=25 Committed Customer Orders Week 1 250 200 Week Week 2 3 300 350 350 350 Week 4 300 325 Week 5 300 250 Week 6 250 275 Week 7 200 175 Week 8 100 110 ATP:DStep by Step Solution