Question
Can someone explain to me the difference between these two questions? I find 88,000 to be the answer to both questions, but I feel like
Can someone explain to me the difference between these two questions? I find 88,000 to be the answer to both questions, but I feel like that can't be right.
Given the following data, compute equivalent units of production for conversion costs:
Beginning Work in Process8,000 units, 40% complete
Units Completed and Transferred Out90,000 units
Ending Work in Process6,000 units, 20% complete.
a. 88,000 b. 91,200 c. 94,400 d. 96,000
Given the following data, compute equivalent units of production for materials costs. Materials are added at the beginning of the process.
Beginning Work in Process8,000 units, 40% complete
Units Completed and Transferred Out90,000 units
Ending Work in Process6,000 units, 20% complete.
a. 88,000 b. 91,200 c. 94,400 d. 96,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started