Question

1 Approved Answer

can you help me complete this Constructing AON and AOA Diagrams Task Predecessors Optimistic Estimate for Duration Most Likely Estimate for Duration Pessimistic Estimate for

can you help me complete this Constructing AON and AOA Diagrams

Task Predecessors Optimistic Estimate for Duration Most Likely Estimate for Duration Pessimistic Estimate for Duration Expected Duration
Start 0 0 0
A Start 6 8 11
B Start 2 6 10
C Start 2 5 9
D A 3 7 14
E A 1 5 8
F C 1 4 9
G C 3 9 14
H B, E, F 5 10 14
I B, D, E, F 6 9 13
J B, E, F, G 8 15 22
End I, J 0 0 0

Consider the following table with activities in a project, predecessors and duration for each activity.

Activity Predecessor Duration in Months
Start 0
A Start 6
B A, E 2
C B 2
D C 3
E Start 1
F A, E 1
G B, F 7
Finish D, G 0

Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.

Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.

Consider the following table with activities in a project, predecessors and durations for each activity.

Task Predecessors Optimistic Estimate for Duration Most Likely Estimate for Duration Pessimistic Estimate for Duration Expected Duration
Start 0 0 0
A Start 6 8 11
B Start 2 6 10
C Start 2 5 9
D A, B 3 7 14
E B, C 1 5 8
F A, B, C 1 4 9
End E, F 0 0 0

Compute the expected durations for each activity using the three point estimation method.

Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.

Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.

Consider the following table with activities in a project, predecessors and durations for each activity.

Compute the expected durations for each activity using the three point estimation method.

Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.

Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Beginning PostgreSQL On The Cloud Simplifying Database As A Service On Cloud Platforms

Authors: Baji Shaik ,Avinash Vallarapu

1st Edition

1484234464, 978-1484234464

More Books

Students also viewed these Databases questions

Question

What are Electrophoresis?

Answered: 1 week ago

Question

9. Describe the characteristics of power.

Answered: 1 week ago

Question

10. Describe the relationship between communication and power.

Answered: 1 week ago