Question
can you help me complete this Constructing AON and AOA Diagrams Task Predecessors Optimistic Estimate for Duration Most Likely Estimate for Duration Pessimistic Estimate for
can you help me complete this Constructing AON and AOA Diagrams
Task | Predecessors | Optimistic Estimate for Duration | Most Likely Estimate for Duration | Pessimistic Estimate for Duration | Expected Duration |
Start | 0 | 0 | 0 | ||
A | Start | 6 | 8 | 11 | |
B | Start | 2 | 6 | 10 | |
C | Start | 2 | 5 | 9 | |
D | A | 3 | 7 | 14 | |
E | A | 1 | 5 | 8 | |
F | C | 1 | 4 | 9 | |
G | C | 3 | 9 | 14 | |
H | B, E, F | 5 | 10 | 14 | |
I | B, D, E, F | 6 | 9 | 13 | |
J | B, E, F, G | 8 | 15 | 22 | |
End | I, J | 0 | 0 | 0 |
Consider the following table with activities in a project, predecessors and duration for each activity.
Activity | Predecessor | Duration in Months |
Start | 0 | |
A | Start | 6 |
B | A, E | 2 |
C | B | 2 |
D | C | 3 |
E | Start | 1 |
F | A, E | 1 |
G | B, F | 7 |
Finish | D, G | 0 |
Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.
Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.
Consider the following table with activities in a project, predecessors and durations for each activity.
Task | Predecessors | Optimistic Estimate for Duration | Most Likely Estimate for Duration | Pessimistic Estimate for Duration | Expected Duration |
Start | 0 | 0 | 0 | ||
A | Start | 6 | 8 | 11 | |
B | Start | 2 | 6 | 10 | |
C | Start | 2 | 5 | 9 | |
D | A, B | 3 | 7 | 14 | |
E | B, C | 1 | 5 | 8 | |
F | A, B, C | 1 | 4 | 9 | |
End | E, F | 0 | 0 | 0 |
Compute the expected durations for each activity using the three point estimation method.
Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.
Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.
Consider the following table with activities in a project, predecessors and durations for each activity.
Compute the expected durations for each activity using the three point estimation method.
Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.
Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started