Can you please draw a Risk Break Down Structure for the below project and the Probability of Occurrence with scores in a table House project

Can you please draw a Risk Break Down Structure for the below project and the Probability of Occurrence with scores in a table

House project

Work breakdown structure (WBS) for building a 5,500 sq ft house, including estimated durations for each task:

Project Deliverable: Complete House

  • Sub-Deliverable: Design and Planning

1.1.1 Task: Architectural Design (30 days)

1.1.2 Task: Structural Engineering (20 days)

1.1.3 Task: Building Permits and Approvals (45 days)

1.2Sub-Deliverable: Site Preparation

1.2.1 Task: Land Clearing (7 days)

1.2.2 Task: Excavation and Grading (14 days)

1.2.3 Task: Utility Connections (10 days)

1.2.4 Task: Foundation Design and Excavation (21 days)

1.3 Sub-Deliverable: Construction

1.3.1 Task: Framing and Roofing (40 days)

1.3.2 Task: Exterior Finishes (30 days)

1.3.3 Task: Interior Walls and Partitions (15 days)

1.3.4 Task: Plumbing and Electrical Systems Installation (30 days)

1.3.5 Task: HVAC Installation (20 days)

1.3.6 Task: Insulation and Soundproofing (10 days)

1.3.7 Task: Flooring Installation (15 days)

1.3.8 Task: Interior Finishes (25 days)

1.3.9 Task: Cabinetry and Countertop Installation (20 days)

1.3.10 Task: Fixture and Appliance Installation (10 days)

1.4 Sub-Deliverable: Exterior

1.4.1 Task: Landscaping and Outdoor Amenities (20 days)

1.4.2 Task: Driveway and Walkway Construction (14 days)

1.4.3 Task: Fencing and Gate Installation (10 days)

1.4.4 Task: Exterior Lighting Installation (7 days)

1.5 Sub-Deliverable: Finalization and Inspection

1.5.1 Task: Final Touches and Clean-up (10 days)

1.5.2 Task: Quality Assurance and Inspection (15 days)

1.5.3 Task: Final Building Code Compliance Check (5 days)

1.5.4 Task: Obtaining Occupancy Permit (30 days)

1.6 Sub-Deliverable: Project Closeout

1.6.1 Task: Documentation and Record Keeping (5 days)

1.6.2 Task: Warranty and Maintenance Information (5 days)

1.6.3 Task: Final Financial Review and Closure (10 days)

Please note that the durations provided are rough estimates and can vary based on factors such as project complexity, availability of resources, and external dependencies.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Statistics

Authors: Robert A Donnelly, Robert Donnelly Jr

2nd Edition

0133852288, 9780133852288

More Books

Students also viewed these General Management questions

Question

What are the short- and long-term effects of stress on the body?

Answered: 1 week ago

Question

5. Give examples of binary thinking.

Answered: 1 week ago