Question
Can you please draw a Risk Break Down Structure for the below project and the Probability of Occurrence with scores in a table House project
Can you please draw a Risk Break Down Structure for the below project and the Probability of Occurrence with scores in a table
House project
Work breakdown structure (WBS) for building a 5,500 sq ft house, including estimated durations for each task:
Project Deliverable: Complete House
- Sub-Deliverable: Design and Planning
1.1.1 Task: Architectural Design (30 days)
1.1.2 Task: Structural Engineering (20 days)
1.1.3 Task: Building Permits and Approvals (45 days)
1.2Sub-Deliverable: Site Preparation
1.2.1 Task: Land Clearing (7 days)
1.2.2 Task: Excavation and Grading (14 days)
1.2.3 Task: Utility Connections (10 days)
1.2.4 Task: Foundation Design and Excavation (21 days)
1.3 Sub-Deliverable: Construction
1.3.1 Task: Framing and Roofing (40 days)
1.3.2 Task: Exterior Finishes (30 days)
1.3.3 Task: Interior Walls and Partitions (15 days)
1.3.4 Task: Plumbing and Electrical Systems Installation (30 days)
1.3.5 Task: HVAC Installation (20 days)
1.3.6 Task: Insulation and Soundproofing (10 days)
1.3.7 Task: Flooring Installation (15 days)
1.3.8 Task: Interior Finishes (25 days)
1.3.9 Task: Cabinetry and Countertop Installation (20 days)
1.3.10 Task: Fixture and Appliance Installation (10 days)
1.4 Sub-Deliverable: Exterior
1.4.1 Task: Landscaping and Outdoor Amenities (20 days)
1.4.2 Task: Driveway and Walkway Construction (14 days)
1.4.3 Task: Fencing and Gate Installation (10 days)
1.4.4 Task: Exterior Lighting Installation (7 days)
1.5 Sub-Deliverable: Finalization and Inspection
1.5.1 Task: Final Touches and Clean-up (10 days)
1.5.2 Task: Quality Assurance and Inspection (15 days)
1.5.3 Task: Final Building Code Compliance Check (5 days)
1.5.4 Task: Obtaining Occupancy Permit (30 days)
1.6 Sub-Deliverable: Project Closeout
1.6.1 Task: Documentation and Record Keeping (5 days)
1.6.2 Task: Warranty and Maintenance Information (5 days)
1.6.3 Task: Final Financial Review and Closure (10 days)
Please note that the durations provided are rough estimates and can vary based on factors such as project complexity, availability of resources, and external dependencies.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started