Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Can you please help me out with the attached documents? I thought I was getting help when I uploaded to the course hero but all

Can you please help me out with the attached documents? I thought I was getting help when I uploaded to the course hero but all it did was upload the case and the documents.

Thank you

image text in transcribed Class: B512 Fiancial Management in Organizations Book: Berk, Jonathan, Peter DeMarzo (2014). Corporate Finance (with Access) 3rd Ed. Pearson. ISBN 9780133424157. Chapter 9 Chapter 7 NPV and Other Investment Rules Gardial Fisheries is considering two mutually exclusive investments (if one is selected the other is eliminated). The projects' expected net cash flows are as follows: Time 0 1 2 3 4 5 6 7 Expected Net Cash Flows Project A Project B ($375) ($575) ($300) $190 ($200) $190 ($100) $190 $600 $190 $600 $190 $926 $190 ($200) $0 a. If each project's discount rate is 12%, which project should be selected? If the discount rate is 18%, what project is the proper choice? @ 12% discount rate @ 18% discount rate discount rate (opportunity cost) = 12% discount rate (opportunity cost) NPV A = NPV A = NPV B = 18% NPV B = b. What is each project's IRR? We find the internal rate of return with Excel's IRR function IRR A = IRR B = c. What is the crossover rate, and what is its significance? Cash flow differential Time 0 1 2 3 4 5 6 7 Incremental IRR rate = d. What is the regular payback period for these two projects? Project A Time period Cash flow Payback 0 (375) 1 (300) 2 (200) 3 (100) 4 600 5 $600 6 $926 Time period Cash flow Payback 0 (575) 1 190 2 190 3 190 4 190 5 $190 6 $190 Project B e. At a rate of 12%, what is the discounted payback period for these two projects? Project A Time period Cash flow Discounted Payback 0 (375) 1 (300) 2 (200) 3 (100) 4 600 5 $600 6 $926 Time period Cash flow Discounted Payback 0 (575) 1 190 2 190 3 190 4 190 5 $190 6 $190 Project B f. What is the profitability index for each project if the discount rate is 12%? PV of future cash flows for A: PI of A: PV of future cash flows for B: PI of B: Chapter 7 NPV and Other Investment Rules Gardial Fisheries is considering two mutually exclusive investments (if one is selected the other is eliminated). The projects' expected net cash flows are as follows: Time 0 1 2 3 4 5 6 7 Expected Net Cash Flows Project A Project B ($375) ($575) ($300) $190 ($200) $190 ($100) $190 $600 $190 $600 $190 $926 $190 ($200) $0 a. If each project's discount rate is 12%, which project should be selected? If the discount rate is 18%, what project is the proper choice? @ 12% discount rate @ 18% discount rate discount rate (opportunity cost) = 12% discount rate (opportunity cost) NPV A = NPV A = NPV B = 18% NPV B = b. What is each project's IRR? We find the internal rate of return with Excel's IRR function IRR A = IRR B = c. What is the crossover rate, and what is its significance? Cash flow differential Time 0 1 2 3 4 5 6 7 Incremental IRR rate = d. What is the regular payback period for these two projects? Project A Time period Cash flow Payback 0 (375) 1 (300) 2 (200) 3 (100) 4 600 5 $600 6 $926 Time period Cash flow Payback 0 (575) 1 190 2 190 3 190 4 190 5 $190 6 $190 Project B e. At a rate of 12%, what is the discounted payback period for these two projects? Project A Time period Cash flow Discounted Payback 0 (375) 1 (300) 2 (200) 3 (100) 4 600 5 $600 6 $926 Time period Cash flow Discounted Payback 0 (575) 1 190 2 190 3 190 4 190 5 $190 6 $190 Project B f. What is the profitability index for each project if the discount rate is 12%? PV of future cash flows for A: PI of A: PV of future cash flows for B: PI of B: Chapter 7 NPV and Other Investment Rules Gardial Fisheries is considering two mutually exclusive investments (if one is selected the other is eliminated). The projects' expected net cash flows are as follows: Time 0 1 2 3 4 5 6 7 Expected Net Cash Flows Project A Project B ($375) ($575) ($300) $190 ($200) $190 ($100) $190 $600 $190 $600 $190 $926 $190 ($200) $0 a. If each project's discount rate is 12%, which project should be selected? If the discount rate is 18%, what project is the proper choice? @ 12% discount rate @ 18% discount rate discount rate (opportunity cost) = 12% discount rate (opportunity cost) NPV A = NPV A = NPV B = 18% NPV B = b. What is each project's IRR? We find the internal rate of return with Excel's IRR function IRR A = IRR B = c. What is the crossover rate, and what is its significance? Cash flow differential Time 0 1 2 3 4 5 6 7 Incremental IRR rate = d. What is the regular payback period for these two projects? Project A Time period Cash flow Payback 0 (375) 1 (300) 2 (200) 3 (100) 4 600 5 $600 6 $926 Time period Cash flow Payback 0 (575) 1 190 2 190 3 190 4 190 5 $190 6 $190 Project B e. At a rate of 12%, what is the discounted payback period for these two projects? Project A Time period Cash flow Discounted Payback 0 (375) 1 (300) 2 (200) 3 (100) 4 600 5 $600 6 $926 Time period Cash flow Discounted Payback 0 (575) 1 190 2 190 3 190 4 190 5 $190 6 $190 Project B f. What is the profitability index for each project if the discount rate is 12%? PV of future cash flows for A: PI of A: PV of future cash flows for B: PI of B

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurial Finance

Authors: Chris LeachJ LeachRonald Melicher

3rd Edition

0324561253, 9780324561258

More Books

Students also viewed these Finance questions

Question

Identify the business benefits of a relational database.

Answered: 1 week ago

Question

1. Too understand personal motivation.

Answered: 1 week ago