CanZinc Company specializes in the mining and refining of rough zinc. The company mine rough zinc from mine A and mine B. The company refines
CanZinc Company specializes in the mining and refining of rough zinc. The company mine rough zinc from mine A and mine B. The company refines the rough zinc in plant 1 and plant 2. A few weeks ago Canzinc received an order of 12,000 tons of refined zinc. To fill this order, Canzinc started mining from tow new mines; mine c and mine D. The following data shows the mining capacity for each mine and the grade of zinc produced in refining. The grade of Zinc represents the volume of refined zinc that can be obtained with 1 ton of rough zinc
Mine | Maximum capacity | Grade of Zinc per ton of rough zinc |
A | 9,000 tons | 0.40 per ton |
B | 8,000 tons | 0.35 per ton |
C | 6,000 tons | 0.50 per ton |
D | 10,000 tons | 0.40 per ton |
Plant 1 can refined 15,000 tons and plant 2 can refine 17,000 tons
The controller of CanZinc wants to minimize the cost of transportation of the rough zinc. He has determined the costs of transportation per ton between the four mines and two plants as follows:
Mine | Plant 1 | Plant 2 |
A | $20 | $15 |
B | $30 | $30 |
C | $35 | $25 |
D | $40 | $45 |
a) Formulate the above as a linear program to minimize the cost of transportation.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started