CAPM Sample Problem In addition to answering the following questions, please post the diagram with your forward/backward chain calculations. Please mark the critical path. (Electronic

CAPM Sample Problem

  • In addition to answering the following questions, please post the diagram with your forward/backward chain calculations. Please mark the critical path. (Electronic and handwritten work are both fine.)
  • What is the project duration?
  • What is the float of activity C?
  • What is the free float of activity C?
  • If management imposes an end time of 22 days what is the project float?
image text in transcribed
C 3days h b 4days 2days e S a 9days 5days 6days h 7 days 8days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management In The Hospitality Industry

Authors: Mike Olsen, Michael D Olsen

2nd Edition

0471292397, 9780471292395

More Books

Students also viewed these General Management questions