Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Car PlantCar Plant (CPCP) designs and produces automotive parts. In 20172017, actual manufacturing overhead is $ 318 comma 000$318,000. CP'sCP's simple costing system allocates manufacturing

Car PlantCar Plant

(CPCP)

designs and produces automotive parts. In

20172017,

actual manufacturing overhead is

$ 318 comma 000$318,000.

CP'sCP's

simple costing system allocates manufacturing overhead to its three customers based onmachine-hours and prices its contracts based on full costs. One of its customers has regularly complained of being charged noncompetitive prices, so

CP'sCP's

controller

DevonDevon

EverettEverett

realizes that it is time to examine the consumption of overhead resources more closely. He knows that there are three main departments that consume overhead resources: design, production, and engineering. Interviews with the department personnel and examination of time records yield the following detailed information:

$

$

Requirement 1. Compute the manufacturing overhead allocated to each customer in

20172017

using the simple costing system that uses machine-hours as the allocation base.

Determine the formula needed to calculate overhead using the simple costing method and then calculate

CPCP's

manufacturing overhead rate for

20172017.

(Round your answer to the nearest cent.)

Total manufacturing overhead

Total machine hours

=

Manufacturing overhead rate

$318,000

5,000

=

$63.60

per machine hour

Calculate the overhead allocated to each customer using the simple costing method. (Round your answers to the nearest whole dollar.)

Machine

Overhead

Customer

Hours Used

Allocated

United Motors

220

$13,992

Anthony Motors

3,300

$209,880

Herman Auto

1,480

$94,128

Requirement 2. Compute the manufacturing overhead allocated to each customer in

20172017

using department-based manufacturing overhead rates. (Abbreviations used: Dept. = Department.)

Determine the formula used to calculate the department-based manufacturing overhead rates:

Manufacturing overhead per dept.

Total hours per dept.

=

Manufacturing overhead rate by dept.

CPCP's

20172017

manufacturing overhead rates by department are as follows:

Manufacturing Overhead Rate

Department

(by Department)

Design

$95

per

CAD-design hour

Engineering

$75

per

engineering hour

Production

$50

per

machine hour

Calculate the overhead allocated to each customer, by department, using the departmental manufacturing overhead rates calculated in the previous step. Calculate the total overhead cost for each department and each customer.

United

Anthony

Herman

Department

Motors

Motors

Auto

Total

Design

Engineering

Production

Total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Government Contracts Audits And Compliance

Authors: Gregory A. Garrett

1st Edition

0808023926, 978-0808023920

More Books

Students also viewed these Accounting questions