Carpet Company's ABC analysis indicates that Manufacturing overhead costs include large costs incurred for setups when a new batch of carpet is started. Carpet Company's
Carpet Company's ABC analysis indicates that Manufacturing overhead costs include large costs incurred for setups when a new batch of carpet is started. Carpet Company's ABC analysis indicates that Manufacturing overhead costs include large costs incurred for setups when a new batch of carpet is started. Carpet Company's ABC analysis indicates that Manufacturing overhead costs include large costs incurred for setups when a new batch of carpet is started.
Week | Number of Batches | Direct Manufacturing Labor-Hours | Manufacturing Overhead Cost | ||||||||||||||
1 | 12 | 30 | $ 1,190 | ||||||||||||||
2 | 15 | 72 | 1,211 | ||||||||||||||
3 | 13 | 36 | 1,004 | ||||||||||||||
4 | 11 | 20 | 917 | ||||||||||||||
5 | 12 | 45 | 1,456 | ||||||||||||||
6 | 16 | 44 | 1,180 | ||||||||||||||
7 | 7 | 38 | 710 | ||||||||||||||
8 | 14 | 70 | 1,316 | ||||||||||||||
9 | 12 | 30 | 1,032 | ||||||||||||||
10 | 7 | 29 | 752 | ||||||||||||||
11 | 8 | 33 | 800 | ||||||||||||||
12 | 10 | 35 | 865 | ||||||||||||||
Do not retype the information above. You should use this sheet as your data sheet and your solution should be on separate | |||||||||||||||||
sheets. | |||||||||||||||||
Part 2 should contain 2-simple regression tables, 1-multiple regression table, and 2-scattergraphs when you are done.--I have done one of the scattergraphs and simple regression using direct labor for you. | |||||||||||||||||
Required: | |||||||||||||||||
1. Prepare 2 scattergraphs and 2 simple regression analyses***** to estimate the Manufacturing Overhead costs using each of the | |||||||||||||||||
cost drivers above. Make sure you show the equation of the line and R-squared on each of your scattergraphs. | |||||||||||||||||
I have gone ahead and developed the simple regression table and the scattergraph using Direct Manufacturing labor hours as the cost driver (I.e. independent variable) | |||||||||||||||||
You do not need to redo these, but you may want to use these as a verification that you know how to develop a scattergraph and a simple regression table. | |||||||||||||||||
The output and chart for your simple regression should be on separate sheets that should be named appropriately. | |||||||||||||||||
Type the equation of the line under the regression output on each of the simple regression worksheets. | |||||||||||||||||
To make a scattergraph with data from nonadjacent columns highlight the X data (i.e. independent variable-cost driver) first and then hold down the | |||||||||||||||||
control (ctrl) key and highlight the Y data (i.e. the dependent variable-cost). | |||||||||||||||||
If you have done your scattergraphs correctly the equation of the line and the R-squared should match the output you have on your regression table. | |||||||||||||||||
(i.e. R-squared, Intercept, and X Variable.) Hint: the Y(dependent) variable is the same in all your scattergraphs and regression analyses--which is Manufacturing overhead cost. | |||||||||||||||||
2. Prepare a multiple regression table using batches and direct labor hours for the independent variables. Do not try to prepare a scattergraph, since you cannot make a chart with multiple X's. | |||||||||||||||||
Using the output from the multiple regression, give the equation to estimate manufacturing overhead costs in terms of these | |||||||||||||||||
2 cost drivers. Type out the equation of the line on your multiple regression worksheet. | |||||||||||||||||
X1 | Number of batches | ||||||||||||||||
X2 | Direct Manufactuirng labor hours | ||||||||||||||||
3. Assuming the following level of cost-driver volume, what is the estimated Manufacturing overhead | |||||||||||||||||
cost using simple regression for each of the cost drivers and using multiple regression. You should have | |||||||||||||||||
3 computations for this answer. I have completed one of the answers for you. You must use cell referencing from your regression tables to compute the estimated cost to earn credit for part 3. | |||||||||||||||||
Cost Drivers (independent variables): | |||||||||||||||||
Number of batches | 13 | ||||||||||||||||
Direct Manufacturing labor hours | 37 | ||||||||||||||||
Solution: | |||||||||||||||||
Direct Manufacturing labor hours | |||||||||||||||||
Answer: | |||||||||||||||||
$ 1,008.78 | |||||||||||||||||
You need to answer: | |||||||||||||||||
Number of batches | |||||||||||||||||
Answer: | |||||||||||||||||
Multiple regression | |||||||||||||||||
Answer | |||||||||||||||||
4. Using the simple and multiple regression analyses output tables, what independent variable(s) would you recommend | |||||||||||||||||
to estimate the Indirect Manufacturing Overhead Costs? Why? Your response should be at least 75 words and discuss the R-Squared. | |||||||||||||||||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started