Carrying cost Input for Planning Workers per day Hours per month, MOS/month = 50 Overtime restriction Maximum Overtime (h) Carrying cost $3.00 per unit per

Carrying cost Input for Planning Workers per day Hours per month, MOS/month = 50 Overtime restriction Maximum Overtime (h)
Carrying cost $3.00 per unit per month Regular Overtime Subcontract.
Labour input 1.6 hours per unit Cost per unit January 9 0 0 TRUE 720.0
Regular pay rate $10.00 per hour $16.00 February 9 0 0 TRUE 612.0
Overtime pay rate $13.00 per hour $20.80 March 9 0 0 TRUE 756.0
Subcontracting cost $22.00 per unit per month $22.00 April 9 0 0 TRUE 720.0
Full workday hours 8 per day May 9 0 0 TRUE 792.0
incr. daily prod. rate $200.00 per unit for admin and training newly hired June 9 0 0 TRUE 720.0
Decr. daily prod. rate $400.00 per unit for admin and compensating layed off Total 0 0
Workers in December 5 Output
Forecasting Information Demand Produc-tion days Demand per day Production per month Inventory change Ending inventory Inventory cost Labour cost Hires and layoffs Sub-contracting Total cost
January 700 20 35 900 200 200 $600.00 $14,400.00 $0.00 $15,000.00
February 595 17 35 765 170 370 $1,110.00 $12,240.00 $0.00 $0.00 $13,350.00
March 735 21 35 945 210 580 $1,740.00 $15,120.00 $0.00 $0.00 $16,860.00
April 1020 20 51 900 -120 460 $1,380.00 $14,400.00 $0.00 $0.00 $15,780.00
May 1200 22 61 990 -210 250 $750.00 $15,840.00 $0.00 $0.00 $16,590.00
June 1150 20 58 900 -250 0 $0.00 $14,400.00 $0.00 $0.00 $14,400.00
Total/Average 5400 120 45 5400 0 1860 $5,580.00 $86,400.00 $0.00 $0.00 $91,980.00
Additional Restrictions Apply in the order below and report results Answer field task d)
1. Hiring the company only hires full time workers
2. Overtime 50% of full-time hours per month cannot be exceeded
3. Subcontracting 50 units per month Minimum Order Size (MOS)
4. Ending inventory 400 units maximum ending inventory capacity

a) One important change to the basic information is that in December, 5 workers were employed on a full-time basis. Because of this, the cost of hiring more workers in January needs to be added to the total cost. Enter a formula in cell J12 to calculate the cost of hiring more workers(and potentially laying workers off) in January.

b) In the answer field for task b), state whether the level strategy has produced a feasible solution. Feasible means that it meets all four restrictions.

c) Using the same formula. It currently shows the level strategy solution (9 workers employed full time every month). Find a solution with regular work time only (no overtime and no subcontracting) that meets all four restrictions and has the lowest cost of feasible regular work only solutions. Describe your solution.

Also using the same formula implement a chase strategy where the number of full-time workers per month is chosen that meets the lowest per day demand in a month and in which the gap between monthly production and monthly demand is filled by subcontracting so that the ending inventory is zero at the end of each month. Describe your solution and comment on whether the solution is feasible.

d)Using the same formula. It currently shows the level strategy solution (9 workers employed full time every month). Strictly implement a chase strategy in which the number of full-time workers per month is chosen that meets the lowest per day demand in a month and in which the gap between monthly production and monthly demand is filled by overtime production so that the ending inventory is zero at the end of each month. Describe the solution and comment on whether the solution is feasible.

Please explain with all steps.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions