Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Cascade Inc. has provided the following information: Standards: Per unit Direct materials 5.5 lbs @ $4.00/lb $ 22.00 Direct labor 1.0 hours @ $11.5/hour 11.50

Cascade Inc. has provided the following information:

Standards: Per unit
Direct materials 5.5 lbs @ $4.00/lb $ 22.00
Direct labor 1.0 hours @ $11.5/hour 11.50
Variable overhead 2.5 hours @ $10.5/hour 26.25
Fixed overhead 16.00
Total $ 75.75

Budgeted production = 4,780 units

Actual results
Direct materials 30,600 lbs $ 127,470
Direct labor 11,870 actual hours $ 154,600
Variable overhead $ 118,210
Fixed overhead $ 76,800
Units produced 5,200 units

Calculate the direct materials price variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Committee Essentials

Authors: Curtis C. Verschoor

1st Edition

0471699594, 978-0471699590

More Books

Students also viewed these Accounting questions

Question

What is routing?

Answered: 1 week ago

Question

6. Explain the strengths of a dialectical approach.

Answered: 1 week ago