Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Case 7 . 1 Bridgecon Contractors Bridgecon Construction Company specializes in the detailed design and construction of steel and concrete bridges. The first phase of

Case 7.1 Bridgecon Contractors
Bridgecon Construction Company specializes in
the detailed design and construction of steel and
concrete bridges. The first phase of the company's
project management methodology, Initiation,
includes identification of project opportunities and
assessment of each project's risks and alignment
with strategic goals. Bridgecon's marketing depart-
ment identified an opportunity: a well-known
bridge architect recently completed the concept
design for a cable-stayed bridge intended to cross
over electrified railway lines. Senior managers felt
the company could handle the project and decided
to pursue it; this marked the end of the first phase.
The project next enters the second phase, Esti-
mating, which includes site visits by the estimat-
ing team, review of available resources and skills,
detailed risk assessment, and preparing a prelimi-
nary plan for detailed design, procurement, logistics,
and construction. The phase includes activities A and
B in Table 7.6, which are necessary to prepare the bid
for building the bridge. The phase concludes with a
presentation to the customer, the rail authority.
The project manager and the estimating team
meet with the architect and structural engineers
who produced the concept design to acquaint
themselves with the design. They then meet with
subcontractors who they might choose to con-
struct the pilings and fabricate steel components.
Following these meetings the "Initial Duration
Estimate" and "Initial Cost Estimate" are com-
pleted, shown in Table 7.6.
The RFP (request for proposal) for building
the bridge says acceptance of the plan by the rail
authority is one criterion for selecting a contractor.
Early on it becomes evident that starting with activ-
ity D and until the completion of activity S, opera-
tion of one of the railway lines under the bridge
will be impaired, although an informal discussion
with the rail authority indicates that this might be
acceptable. During a subsequent meeting, however,
the rail authority expresses concern that the impair-
ment will last 17 weeks, and requests Bridgecon to
find ways to reduce that time. The estimating team
suggests the following possibilities:
The duration of activity N could be reduced
from 1 week to half a week by using additional
trucks. The additional cost would be $33,000.
An alternative subcontractor for piling is
approached. This subcontractor says it will be
able to halve the time of Activity H for a total
cost of $960,000.
Two ways are identified to shorten the dura-
tion of activity D. First, additional temporary
workers could be employed. This would
reduce the duration to 3 weeks, and increaseTable 7.6 Activities for Constructing the Cable-Stayed Bridge
the cost to $147,000. Second, a team of work-
ers highly skilled in this procedure (and their
equipment) could be temporarily reallocated
from another project. Adding this team and
temporary workers to the original team could
lead to completing the work in 1 week. The
manager of the other project estimates that
the reallocation would cause him to forfeit
an incentive fee of $150,000 for finishing his
project early. The managers of the two projects
agree that, should the reallocation be made,
the value of incentive fee would be booked as
a cost against the cable-stayed bridge project
and transferred as a bonus to the other project.
The duration of activity F can be reduced to 3
weeks, but would increase the activity's cost to
$730,000. It could be reduced to 2 weeks, but
would cost $820,000.
The duration of activity Q can be reduced to 2
weeks, but the activity would cost $2,929,000.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ignite Your Lyfe Self Esteem Through Entrepreneurship

Authors: Jameelah Wilkerson

1st Edition

979-8458529761

More Books

Students also viewed these General Management questions