Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Case 7 . 1 Bridgecon Contractors Bridgecon Construction Company specializes in the detailed design and construction of steel and concrete bridges. The first phase of
Case Bridgecon Contractors
Bridgecon Construction Company specializes in
the detailed design and construction of steel and
concrete bridges. The first phase of the company's
project management methodology, Initiation,
includes identification of project opportunities and
assessment of each project's risks and alignment
with strategic goals. Bridgecon's marketing depart
ment identified an opportunity: a wellknown
bridge architect recently completed the concept
design for a cablestayed bridge intended to cross
over electrified railway lines. Senior managers felt
the company could handle the project and decided
to pursue it; this marked the end of the first phase.
The project next enters the second phase, Esti
mating, which includes site visits by the estimat
ing team, review of available resources and skills,
detailed risk assessment, and preparing a prelimi
nary plan for detailed design, procurement, logistics
and construction. The phase includes activities A and
B in Table which are necessary to prepare the bid
for building the bridge. The phase concludes with a
presentation to the customer, the rail authority.
The project manager and the estimating team
meet with the architect and structural engineers
who produced the concept design to acquaint
themselves with the design. They then meet with
subcontractors who they might choose to con
struct the pilings and fabricate steel components.
Following these meetings the "Initial Duration
Estimate" and "Initial Cost Estimate" are com
pleted, shown in Table
The RFP request for proposal for building
the bridge says acceptance of the plan by the rail
authority is one criterion for selecting a contractor.
Early on it becomes evident that starting with activ
ity and until the completion of activity opera
tion of one of the railway lines under the bridge
will be impaired, although an informal discussion
with the rail authority indicates that this might be
acceptable. During a subsequent meeting, however,
the rail authority expresses concern that the impair
ment will last weeks, and requests Bridgecon to
find ways to reduce that time. The estimating team
suggests the following possibilities:
The duration of activity could be reduced
from week to half a week by using additional
trucks. The additional cost would be $
An alternative subcontractor for piling is
approached. This subcontractor says it will be
able to halve the time of Activity for a total
cost of $
Two ways are identified to shorten the dura
tion of activity D First, additional temporary
workers could be employed. This would
reduce the duration to weeks, and increaseTable Activities for Constructing the CableStayed Bridge
the cost to $ Second, a team of work
ers highly skilled in this procedure and their
equipment could be temporarily reallocated
from another project. Adding this team and
temporary workers to the original team could
lead to completing the work in week. The
manager of the other project estimates that
the reallocation would cause him to forfeit
an incentive fee of $ for finishing his
project early. The managers of the two projects
agree that, should the reallocation be made,
the value of incentive fee would be booked as
a cost against the cablestayed bridge project
and transferred as a bonus to the other project.
The duration of activity can be reduced to
weeks, but would increase the activity's cost to
$ It could be reduced to weeks, but
would cost $
The duration of activity can be reduced to
weeks, but the activity would cost $
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started