Case: PMI Project Planning and implementing a national conference for a society that will draw about 1000 attendees is a major project. The tasks involved

Case: PMI Project

Planning and implementing a national conference for a society that will draw about 1000 attendees is a major project. The tasks involved in hosting such an event are considerable and involve selecting a program committee, choosing a theme, contacting exhibitors, making local arrangements, planning the program, and on and on.

Pittsburgh was selected as the host city/chapter for the 1992 Project Management Institute's annual September seminar/symposium. The objectives for the event were three: (1) to deliver a high-quality, value-added program that would be useful and last for years to come, (2) to offer a social and guest program that would reflect well on the host city, and (3) to meet strict financial criteria. The first task after selecting the city and hotel facilities was to put together the project team and chairperson. This included managers in charge of each of the tracks, the social program, the local arrangements, and all the other details. The project team was organized using a functional approach. Pittsburgh PMI Chapter officers had most of the primary responsibilities, with members from nine other chapters assisting in other duties.

Next was the development of the work breakdown structure, shown below.

SIS Project Management

Recruit Project Team

Establish Organizational Procedures

Establish CAO Support Levels and Budget

Issue Reports to VP-Tech and Board of Directors

Develop SIS Goals and Objectives

Assemble and Issue Post SIS Report

Technical Program

Develop SIS Theme

Strategize Tracks and SIGs

Recruit Technical Program Team

Develop Selection Process Procedures

Interface with Education Committee on Workshops

Plan and Issue Call for Papers/Panel Discussion

Recruit Invited Papers/Panel Discussions

Recruit Moderators

Develop and Issue a Master Schedule for Presentations

Select Printer

Plan and Issue Abstract Books and Proceedings

Organize Awards for Speakers' Breakfasts

Identify Audio/Visual Requirements

Develop and Issue Post-SIS Technical Report

Social Guest Program

Establish Objectives

Identify Available Activities

Analyze Cost-Benefit

Identify Recommendations

Complete Contracts

Recruit Staff

Speakers

Identify Candidates and Related Benefits and Costs

Make Recommendations and Obtain Approval

Complete Contracts

Maintain Periodic Contact

Host Speakers

Publicity/Promotion

Theme Establishment and Approval

Logo Development and Approval

Video Production Promotional Materials

Identification and Approval

Advertising: PMI, Public and Trade Media Releases

Regional Newsletter Articles

Finance

Initiate Code of Accounts

Develop Procedures for Financial Operation

Develop Independent Auditing Procedure

Initiate Separate Banking Account

Develop Cash Flow Estimates/Projections

Develop and Issue Standard Reports

Interact with CAO on Account Reconciliation

Develop and Issue Post-SIS

Financial Report

Corporate Sponsorship

Establish Participation Philosophy

Target Prime Corporations

Solicit Participation Recognition

Facilities Vendor/CAO Support

Contract with Host and Backup Hotels

Staff Recruiting

(Details to Be Identified and Scheduled with PMI Executive Director and Events Manager

In the WBS, the major task was the development of a program that offered 22 workshops composed of 70 technical papers, special panel discussions, and case studies. The technical tracks included engineering and construction, pharmaceuticals, utility software, automotive, R&D, defense, education, and manufacturing. The workshops included sessions on preparing for the PMI certification examinations, learning about Taguchi concepts of statistical quality control, and future practice in project management. All of these also required careful scheduling.

The vendor program included exhibits by dozens of vendors and a large number of showcase sessions for in-depth demonstrations of their wares. The social program included a golf tournament, numerous social activities to meet with colleagues, tours of Pittsburgh's attractions, and a wide variety of entertainment opportunities.

All in all, a conference such as PMI's is as difficult a project as many firms face in their competitive markets.

Question:

Develop process improvement plans for the project that identify weaknesses and bottlenecks, in each category in the work breakdown structure and create ways to improve quality and efficiency.

You are encouraged to use external resources (e.g. websites, literature, etc.) to understand the project better. Also, please state all the assumptions you had to make for your answers.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Research Methods And Audit In General Practice

Authors: David Armstrong, John Grace

1st Edition

0192624547, 978-0192624543

More Books

Students also viewed these Accounting questions