Question
Case Study #2 ( Agile Approach - Relocation Project ) GROUP PROJECT Total points : 35 Project description : You are hired by the SCM
Case Study #2 (Agile Approach - Relocation Project)
GROUP PROJECT
Total points:35
Project description: You are hired by the SCM Faculty Coordinator to move "stuff" of six SCM faculty from theirold offices on the 3rd floor (Hyland Hall) to theirnew offices on the 4th floor (Hyland Hall).
- Items include books, computers, printers and other miscellaneous items. Furniture such as desks, cabinets and bookshelves arenot to be moved.
- Unlimited boxes are available.
- Unpacking boxes isnot part of the project.
- Offices on the 4th floor aremove-in ready.
Tasks and estimated task times are as follows:
Packing and labeling boxes - 6 minutes per box
Loading boxes on dolly - 1 minute per box
Moving loaded dolly (1 trip) from 3rd floor to 4th floor - 25 minutes.
Unloading boxes into new offices - 1 minute per box
Moving empty dolly (1 trip) from 4th floor to 3rd floor - 15 minutes
Cleaning old offices - 10 minutes per office
Sprint meetings (face-to-face) -15 minutes per meeting
Work package #1:Pack/label boxes in old officeand load boxes on dolly.
Work package #2: Clean old office.
Work package #3 (in sequence):Move loaded dolly to new office, unload boxes in new office and return dolly to 3rd floor).
Story point for Work package #1: 3 points per box
Story point for Work package #2: 8 points per clean office
Story point for Work package #3: 5 points per box
NOTE:The following sources can provide definition and description of concepts/terminology used in Agile Approach:
- Agile Handbook,Taymor E. (available in Module: Agile Approach and Scrum Framework in CANVAS).
- The Scrum Guide, Schwaber K. and Sutherland J. (available in Module: Agile Approach and Scrum Framework in CANVAS).
- Agile Practice Guide, Published by Project Management Institute, 2017, https://www.pmi.org/pmbok-guide-standards/practice-guides/agile.
#1)Strategy #1 (18 points)
- Work hours: Starts at 6:00 am;Ends 60 minutes after all new offices are handed over.
- Definition ofDONE: When new office is "handed over" to the client.
- Lunch break: 11:30 - 12:00
- Sprint time-box: 3 hours
Sprint #1: 6:00 - 9:00
Sprint #2: 9:00 - 12:00
Sprint #3: 12:00 - 3:00
- Sprint meetings:
Sprint #1 meeting:6 - 6:15
Sprint #2 meeting:9 - 9:15
Sprint #3 meeting:12 - 12:15
- Two dollies (capacity 10 boxes per dolly) are available.
- Dolly is "parked" on 3rd floor. Dolly needs to be returned to 3rd floor.
Transformation System:
- Person #1 --- For each office, Work package #1PLUS Work package #2 (in sequence).
- Person #2 --- For each office, Work package #3 (Work package #3 can startas soon as Work package #1 is completed).
Office | Estimated number of boxes | Preferred deadline - Handover of new office to the client |
#1 | 5 | 8:00 am |
#2 | 5 | 9:00 am |
#3 | 10 | 10:00 am |
#4 | 10 | 11:00 am |
#5 | 5 | 12:00 pm |
#6 | 5 | 1:30 pm |
#1) COMPLETE TABLES BELOW FOR STRATEGY #1. (20 points)
Person #1 - Work Sequence (Office #): 1,2,3,4,5,6
Person #1 Schedule:
Office | Work package #1 Start time | Work package #1 Finish time |
#1 | ||
#2 | ||
#3 | ||
#4 | ||
#5 | ||
#6 |
Person #1 - Work Sequence (Office #): 1,2,3,4,5,6
Person #1 Schedule:
Office | Work package #2 Start time | Work package #2 Finish time |
#1 | ||
#2 | ||
#3 | ||
#4 | ||
#5 | ||
#6 |
Person #2 - Work Sequence (Office #): 1,2,3,4,5,6
Person #2 Schedule:
Office | Work package #3 Start time | Work package #3 Finish time |
#1 | ||
#2 | ||
#3 | ||
#4 | ||
#5 | ||
#6 |
Completion (DONE) statistics: (Effectiveness)
Office # | Preferred deadline - Handover of new office to the client | Delay in handover of new office (hours: minutes) | |
#1 | |||
#2 | |||
#3 | |||
#4 | |||
#5 | |||
#6 |
Labor statistics (Efficiency)
Worker | Time Worked | Idle Time |
Person #1 | ||
Person #2 |
Sprint Planning: (Work expectedto be completedduring each sprint by each person)
Sprint #
| Person #1 (Office #, Work package) | Person #2 (Office #, Work package) | Sprint Velocity (in Story points) |
Sprint #1 | |||
Sprint #2 | |||
Sprint #3 |
Product Backlog (Ordered list of workat the beginning of each Sprint)
Sprint #
| Product Backlog - Person #1 (Office #, Work package) | Product Backlog - Person #2 (Office #, Work package) |
Sprint #1 | ||
Sprint #2 | ||
Sprint #3 |
Burndown Table:(Work remainingat the beginning of each Sprint)
Sprint # | Person #1 (Work remaining in Story points) | Person #2 (Work remaining in Story points) |
Sprint #1 | ||
Sprint #2 | ||
Sprint #3 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started