Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

CASE STUDY Should Packing Be Postponed to the DC? Penang Electronics (PE) is a contract manufacturer that produces and packages private-label products for several

 
 student submitted image, transcription available below 

student submitted image, transcription available below 


 

CASE STUDY Should Packing Be Postponed to the DC? Penang Electronics (PE) is a contract manufacturer that produces and packages private-label products for several retail chains, including Target, Best Buy, Staples, and Office Max. In each case, the basic products are identi- cal, with the only difference being the labeling and the packaging. Thus, the labeled and packed version of the product destined for Target cannot be sent to Best Buy. Currently, a production facility in Malaysia is used to manufacture, label, and pack all products. The manu- facturing facility replenishes a DC in St. Louis, from which the contract manufacturer fills all customer orders. The manufacturing and transportation lead time from Penang to St. Louis is nine weeks. PE uses a con- tinuous review policy to manage inventories at its DC and aims to provide a cycle service level of 95 percent for each product to every customer. The previous month had been very challenging because Best Buy requested 5,000 additional units beyond what was available at the DC, whereas Target ordered 3,500 fewer units and Staples ordered 4,000 fewer units. Even though there was sufficient product inventory available at the DC (in the form of the basic product), PE could not meet the Best Buy request because the excess inventory available was labeled and packed for other customers. The DC had leftover inventory from Target and Staples, which unfortunately could not be used to serve Best Buy. PE had lost business and surplus inventory all because of the wrong labels and packaging. Labeling and Packaging at the DC The vice president of supply chain at PE proposed post- poning the final labeling and packaging to the DC. Her logic was that postponing labeling and packaging to the DC would allow PE to use all available inventories to serve any customer. In particular, the situation that arose in the TABLE 12-9 previous month when Best Buy did not get its entire order could have been avoided through postponement. If packag- ing was shifted to the DC, the lead time of manufacturing and transporting the basic product from Malaysia would continue to be about nine weeks. Labeling and packaging were relatively quick steps and the response time from the DC to the customer was not expected to change. The DC management was opposed to this idea because it would add additional work that was different from what they had done so far. A detailed study of the production process had shown that labeling and packag- ing at the DC cost $2 per unit more than the cost of label- ing and packaging in Malaysia. DC management believed that this increase in cost would be held against them once the process was changed, and they would be under con- stant pressure to lower cost. They also believed it would complicate the work they did when filling an order and could adversely impact customer service. Evaluating the Two Options To evaluate the two options, a team from both manufactur ing and the DC was set up. The team decided to focus its analysis on three major product categories-computers, printers, and scanners, and four major customers-Target, Best Buy, Staples, and Office Max. Weekly demand for each product and customer is shown in Table 12-9. In each case, "Mean" indicates the average weekly demand, and "SD" indicates the standard deviation of weekly demand. All demand was assumed to be normally distributed. PE incurred a total cost of $1,000 per computer, $300 per printer, and $100 per scanner. Given the short life cycle of these products, PE used a holding cost of 30 percent when making its inventory decisions. The team analyzed the impact of postponement on safety inventories before mak- ing a final recommendation. Distribution of Weekly Demand by Product and Customer Computers Printers Scanners Mean SD Mean SD Mean SD Target 1,000 700 2,000 1,000 4,000 1,000 Best Buy 700 600 1,500 800 4,500 900 Office Max 800 600 1,200 600 2,000 700 Staples 500 400 900 500 1,400 500 Questions 1. What is the annual inventory cost of the current system in which product is produced, labeled, and packed in Malay- sia before being shipped to the DC? 2. How would the inventory cost change if labeling and pack- aging were moved to the DC? 3. How should PE set up its production, labeling, and pack- aging processes? Does your answer change if the addi- tional cost of labeling and packaging at the DC is reduced to $1 (from the current value of $2)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Based on the provided case study and questions here is a complete answer 1 What is the annual inventory cost of the current system in which the product is produced labeled and packed in Malaysia befor... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Management

Authors: Andrew J DuBrin

10th Edition

0996757872, 9780996757874

More Books

Students also viewed these General Management questions

Question

Solve the Initial Value Problem. y' = y 2 sin x, y() = 2

Answered: 1 week ago

Question

Personal role: This consists of service to family and friends.

Answered: 1 week ago