Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Change Orders You are the a nstruction Manager on $12,000,000 be asked to prepare a combined change order complete with the following documents mbi Swer

image text in transcribed
image text in transcribed
Change Orders You are the a nstruction Manager on $12,000,000 be asked to prepare a combined change order complete with the following documents mbi Swer RhabilitationRojed. Ybu will 1. Aletter to the Owner which will be the instructor of the Course describing the change order in accordance with the Lecture notes. Your letter should indude the reason for the change order, the scope of the change order and a summary of the change order as follows: Original Contract Amount: $5.00 Previous Ohange Orders $1.00 Current Contract Amount: $6.00 Amount of this Ohange Order: $2.00 Amended Oontract Amount: $8.00 2 The Form of the Ohange Order 3 Time and Material Spreadsheet Part 1 The Owner of the Project has directed that an additional 625 linear feet of combined sewer be ed to the ntract. The G neral antrador has eed to perform the workunder the existing unit prices in the contract. There will be a good deal of additional restoration work that will be required induding sidewalks, storm drainage, traffic striping paving and landscaping. The General Contractor (CQ has to subcontract the paving trafficstriping and landscaping to other contractors As the Construction Manger you prepared the scope of work for this additional work. The following raw unit prices induding labour, materials and equipment (profit and overhead have not been applied, but the Oontradtor is eligble for profit and overhead as spedfied on page 3) to perform the work Description Performed By Quantity Unit Unit Price 625 $1,200 $20,100 $15 $25 $85 $2,750 $60 Linear Feet 96" Combined Sewer Hpe General Contractor General Contractor General Contractor Manholes Each Excavation and Disposal Dense Graded Aggregate General Calcte Cubic Yards Contractor General Linear Foot Each Square Yards 310 15" Reinforoed Ape Sorm Inlets Concrete Sdewalks General 6 Contractor GeneralCalculate S Contractor Contractor Subcontractor aonarete Curb General | culate! Linear Foet $15 Subcontractor Calculate Square Feet$3.50 Paving Traffic Sripping Landscaping $5,000 $25,000 p Sum alate the total cot of the dange order based upon the unit prices and apply the overhead and profit factors described later in this document. You will calculate the quantities based upon the attached sketch Change Orders You are the a nstruction Manager on $12,000,000 be asked to prepare a combined change order complete with the following documents mbi Swer RhabilitationRojed. Ybu will 1. Aletter to the Owner which will be the instructor of the Course describing the change order in accordance with the Lecture notes. Your letter should indude the reason for the change order, the scope of the change order and a summary of the change order as follows: Original Contract Amount: $5.00 Previous Ohange Orders $1.00 Current Contract Amount: $6.00 Amount of this Ohange Order: $2.00 Amended Oontract Amount: $8.00 2 The Form of the Ohange Order 3 Time and Material Spreadsheet Part 1 The Owner of the Project has directed that an additional 625 linear feet of combined sewer be ed to the ntract. The G neral antrador has eed to perform the workunder the existing unit prices in the contract. There will be a good deal of additional restoration work that will be required induding sidewalks, storm drainage, traffic striping paving and landscaping. The General Contractor (CQ has to subcontract the paving trafficstriping and landscaping to other contractors As the Construction Manger you prepared the scope of work for this additional work. The following raw unit prices induding labour, materials and equipment (profit and overhead have not been applied, but the Oontradtor is eligble for profit and overhead as spedfied on page 3) to perform the work Description Performed By Quantity Unit Unit Price 625 $1,200 $20,100 $15 $25 $85 $2,750 $60 Linear Feet 96" Combined Sewer Hpe General Contractor General Contractor General Contractor Manholes Each Excavation and Disposal Dense Graded Aggregate General Calcte Cubic Yards Contractor General Linear Foot Each Square Yards 310 15" Reinforoed Ape Sorm Inlets Concrete Sdewalks General 6 Contractor GeneralCalculate S Contractor Contractor Subcontractor aonarete Curb General | culate! Linear Foet $15 Subcontractor Calculate Square Feet$3.50 Paving Traffic Sripping Landscaping $5,000 $25,000 p Sum alate the total cot of the dange order based upon the unit prices and apply the overhead and profit factors described later in this document. You will calculate the quantities based upon the attached sketch

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Find a singular 2 2 matrix satisfying A2 = A.

Answered: 1 week ago