Changes may be accomplished three ways: (1) by Change Order (CO), (2) by Construction Change Directive (CCD), or (3) by an order for a minor
Changes may be accomplished three ways: (1) by Change Order (CO), (2) by Construction Change Directive (CCD), or (3) by an order for a minor change in the work. Group of answer choices True False