Question
CHAPTER 10: See information in Textbook for Exercise 10-50. I need to change two numbers. Change the number of units produced to be 410,000 and
CHAPTER 10: See information in Textbook for Exercise 10-50. I need to change two numbers. Change the number of units produced to be 410,000 and the number of pounds of materials purchased to be 2,075,000 instead of the quantities given for these in the exercise.
10-50
At the beginning of the year, Crag Company had the following standard cost sheet for one of its plastic products.
Direct materials ( 5 lbs @ 54.00) $20.00
Direct Labor ( 2 hours @ 15.00) 30.00
Standard prime cost per unit 50.00
the actual results for the year are as follows:
a. Units produced: 400,000
b. Materials purchased: 2,060,000 pounds @ 3.95
c. Materials used: 2,100,000 pounds
d. Direct labor: 825,000 hours @ 14.85
1. Compared price and usage variances for materials.
2. Compute labor rate efficiency variances, using both the formula and columnar approaches.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started