Chapter 6 In-class assignment The project information for the custom orer project of the Air Control Company
No answer yet for this question.
Ask a Tutor
Question:
Chapter 6 In-class assignment | |||||
The project information for the custom orer project of the Air Control Company | |||||
is presented here. Draw a project network AON diagram for this project | |||||
Compute the early and late activity times and the slack. Identify the Critical Path. | |||||
ID | Description | Predecessor | Time | ||
A | Order Review | None | 5 | ||
B | Order standard parts | A | 8 | ||
C | Produce standart parts | A | 3 | ||
D | Design custom parts | B | 6 | ||
E | Software Development | B | 15 | ||
F | Manufacture custom hardware | C,D | 10 | ||
G | Assemble | F | 5 | ||
H | Test | E,F,G | 20 | ||
NOTE: Be sure to include a legend for your network solution. | |||||
Chapter 6 Exercise 8 | This exercise is for you to practice if you wish to do so. | ||||
The project information for the custom orer project of the Air Control Company | |||||
is presented here. Draw a project network AON diagram for this project | |||||
Compute the early and late activity times and the slack. Identify the Critical Path. Please Identify the Critical Path with the chart. |