Chapter 6 , Question 3 Given the following production plan, use a ( a ) chase production strategy and ( b ) level production strategy

Chapter 6, Question 3
Given the following production plan, use a (a) chase production strategy and (b) level production strategy to compute the monthly production, ending inventory/(backlog) and workforce levels. A worker can produce 50 units per month. Assume that the beginning inventory in January is 500 units, and the firm desires to have 200 units of inventory at the end of June.
Month
JAN
FEB
MAR
APR
MAY
JUN
Demand
2000
3000
5000
6000
6000
2000
Production
Ending Inventory
Workforce
Q1a
HomeworkAnsweredDue Today, 11:00 PM
In a chase production strategy, what is the monthly production in February?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
3000
Submitted:Answered1 attempt left
Resubmit
Change your responses to resubmit
Q1b
HomeworkAnsweredDue Today, 11:00 PM
In a chase production strategy, what is the ending inventory/backlog in May?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
0
Submitted:Answered1 attempt left
Resubmit
Change your responses to resubmit
Q1c
HomeworkAnsweredDue Today, 11:00 PM
In a chase production strategy, what is the size of the workforce in June?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
44
Submitted:Answered1 attempt left
Resubmit
Change your responses to resubmit
Q1d
HomeworkAnsweredDue Today, 11:00 PM
In a level production strategy, what is monthly production in June?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
3950
Submitted:Answered1 attempt left
Resubmit
Change your responses to resubmit
Q1e
HomeworkAnsweredDue Today, 11:00 PM
In a level production strategy, what is the inventory/backlog in May (enter backlog as a negative number)?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
-1750
Submitted:Answered1 attempt left
Resubmit
Q1f
HomeworkAnsweredDue Today, 11:00 PM
In a level production strategy, what is the workforce required in March?
Type your numeric answer and submit
Numeric Answer - Type your numeric answer and submit
79
Submitted:Answered1 attempt left
Resubmit
Change your responses to resubmit

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions