Chapter 7 Discussion Question 6 1. Explain how earned value management (EVM) can be used to control costs and measure project performance and speculate as
Chapter 7 Discussion Question 6
1. Explain how earned value management (EVM) can be used to control costs and measure project performance and speculate as to why it is not used more often. What are some general rules of thumb for deciding if cost variance, schedule variance, cost performance index, and schedule performance index numbers are good or bad?
2. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value. EV is the earned value, AC is the actual cost, and BAC is the budget at completion.
PV = $23,000
EV = $20,000
AC = $25,000
BAC = $120,000
a. What is the cost variance, schedule variance, cost performance index (CPI),
and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead or schedule or behind schedule? Is it under
budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the
project performing better or worse than planned?
d. Use the schedule performance index (SPI) to estimate how long it will take to
finish this project.
e. Sketch the earned value chart based for this project, using Figure 7-5 as a guide.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started