Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

CHAPTER 9 BS PROJECT MANAGEMENT 331 Activity 9.1 Project planning exercise The scenario You are required to construct a project plan for the following BIS

image text in transcribed
image text in transcribed
CHAPTER 9 BS PROJECT MANAGEMENT 331 Activity 9.1 Project planning exercise The scenario You are required to construct a project plan for the following BIS development project. Your objective is to schedule the project to run in the shortest time possible. The plan should include all activities, the estimated, elapsed and effort time, and who is to perform each activity in addition, it is necessary to indicate the sequence in which all the tasks will take place. The programs can be scheduled in any order but for each programs the design stage must come first, followed by the programming and finally the documentation Within the context of the extrose, you can assume that the detailed systems analysis has already been carried out and that it is now necessary to perform the design programming and documentation activities. For the purposes of this exercise, we will not include the testing and implementation phases Present your project plan in the form of a Gantt charte Fgure to the showing each task, the sequence in which tasks will be performed the estimated effort and elased time and the resource allocated to each task day 4 days 3 days The activities There are the programs in the system. Each has a deterent level of officulty . Program 1 Difficult Program 2 Easy - Program Moderate Program 4 Moderate . Program 5 Difficult For each level of difficulty, the design, programming and documentation tasks take different amounts of effort time Design Easy peogr Moderate programs 2 days Dillicult programs Programming Easy programe 1 day Moderate programs Difficult programs 6 days Documentation Enny programme day . Moderate program 2 days Difficult programs 3 days Resources In order to complete the project plan, you need to know what resources you have avata For each resource, there are two variables: Work rate. This describes the speed at which the resource works e a work rate of 1.0 means that a tank scheduled to take one day should only take one day to complete satisfactorily, a wosk rate of 15 means that a task scheduled for three daye should only take two days etc.) Avity. Each resource will be available for certain amounts of time during the weak 100% availability = 5 days per week, 50% availability=2.5 days per week etc. In planning your project, work to units of half a day. For simplioty, any task which requires a fraction of fait a day should be rounded up leg 16 days should be rounded up to 2 days) Also a resource can only be scheduled for one task at any one time! 332 PART 2 BUSINESS INFORMATION SYSTEMS DEVELOPMENT Resource availability System designer 1 (SDI) - Work rate 1.0 Availability 100% Systems designer 2 (S02 Work rate 1.5 Arailability Systorns designer 3 (50) Work rate 0.5 Availability 50% 40% Programmer TIP) Work rate Availability 2.0 40% Programmer 2 (P2) Work rate Availability 1.0 100% Programmer 3 Pa Work rate 0.5 Availability 60% Technical author ! (TAI) (o do the documentation) Work rate 1.0 - Availability 60% 0.5 100% Technical author 2 (TA2) Work rate Availability Technical author 3 (TAS) - Work rate Aaliability 20 40% Tips 1. This mercise will be easier you structure the information well. You could do this by producing three matrious for the design, programming and documentation ass. Each of them should show across the columns three different tasks for easy, moderate and difficult programs. Each row should indicate how long the interent types of workers will take to complete the task. 2. To calculate the length of elapsed time for each cell in the mateix, it is easiest to use this relationship 100 100 Eupsed time of times Aviability Work rate 2. A calculator may helpt 4. When drawing the Gartt chart, you may want to put your best people on the most difficult taaks, as you would on a real project CHAPTER 9 BS PROJECT MANAGEMENT 331 Activity 9.1 Project planning exercise The scenario You are required to construct a project plan for the following BIS development project. Your objective is to schedule the project to run in the shortest time possible. The plan should include all activities, the estimated, elapsed and effort time, and who is to perform each activity in addition, it is necessary to indicate the sequence in which all the tasks will take place. The programs can be scheduled in any order but for each programs the design stage must come first, followed by the programming and finally the documentation Within the context of the extrose, you can assume that the detailed systems analysis has already been carried out and that it is now necessary to perform the design programming and documentation activities. For the purposes of this exercise, we will not include the testing and implementation phases Present your project plan in the form of a Gantt charte Fgure to the showing each task, the sequence in which tasks will be performed the estimated effort and elased time and the resource allocated to each task day 4 days 3 days The activities There are the programs in the system. Each has a deterent level of officulty . Program 1 Difficult Program 2 Easy - Program Moderate Program 4 Moderate . Program 5 Difficult For each level of difficulty, the design, programming and documentation tasks take different amounts of effort time Design Easy peogr Moderate programs 2 days Dillicult programs Programming Easy programe 1 day Moderate programs Difficult programs 6 days Documentation Enny programme day . Moderate program 2 days Difficult programs 3 days Resources In order to complete the project plan, you need to know what resources you have avata For each resource, there are two variables: Work rate. This describes the speed at which the resource works e a work rate of 1.0 means that a tank scheduled to take one day should only take one day to complete satisfactorily, a wosk rate of 15 means that a task scheduled for three daye should only take two days etc.) Avity. Each resource will be available for certain amounts of time during the weak 100% availability = 5 days per week, 50% availability=2.5 days per week etc. In planning your project, work to units of half a day. For simplioty, any task which requires a fraction of fait a day should be rounded up leg 16 days should be rounded up to 2 days) Also a resource can only be scheduled for one task at any one time! 332 PART 2 BUSINESS INFORMATION SYSTEMS DEVELOPMENT Resource availability System designer 1 (SDI) - Work rate 1.0 Availability 100% Systems designer 2 (S02 Work rate 1.5 Arailability Systorns designer 3 (50) Work rate 0.5 Availability 50% 40% Programmer TIP) Work rate Availability 2.0 40% Programmer 2 (P2) Work rate Availability 1.0 100% Programmer 3 Pa Work rate 0.5 Availability 60% Technical author ! (TAI) (o do the documentation) Work rate 1.0 - Availability 60% 0.5 100% Technical author 2 (TA2) Work rate Availability Technical author 3 (TAS) - Work rate Aaliability 20 40% Tips 1. This mercise will be easier you structure the information well. You could do this by producing three matrious for the design, programming and documentation ass. Each of them should show across the columns three different tasks for easy, moderate and difficult programs. Each row should indicate how long the interent types of workers will take to complete the task. 2. To calculate the length of elapsed time for each cell in the mateix, it is easiest to use this relationship 100 100 Eupsed time of times Aviability Work rate 2. A calculator may helpt 4. When drawing the Gartt chart, you may want to put your best people on the most difficult taaks, as you would on a real project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Accounting

Authors: Frederick D. Choi, Gary K. Meek

6th edition

978-0131588141

Students also viewed these Accounting questions