Answered step by step
Verified Expert Solution
Link Copied!

Question

...
1 Approved Answer

Chapter Exercises 1. A project has been dened to contain the following list of activities along with their required times for completion. Activity No. Activity

image text in transcribed
image text in transcribed
Chapter Exercises 1. A project has been dened to contain the following list of activities along with their required times for completion. Activity No. Activity Time (Weeks) Immediate Predecessors l I Collect requirements 2 I Analyze processes 3 I Analyze data 3 I Design processes 7 Design data 6 - 8 Program 4 9 I Test and document 8 677 10 | Install 2 8,9 a. Draw a network diagram for the activities. b. Calculate the earliest expected completion time. c. Show the critical path. d. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1. 3. Look again at the activities outlined in Problem 1. Assume that during the first week of the project your team discovers that the activity duration estimates were all wrong. Rather than 3 weeks, Activity 2 will take only two weeks to complete,whereas both Activities 4 and 7 will take three times longer than originally estimated. Further, all other activities will take twice as much time to complete. In addition, your team has noticed that additional training is needed. This new activity, number 11, will take one week to complete, and depends on the completion of Activities 10 and 9. Create a new network diagram representing the new earliest expected completion times

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting and Reporting

Authors: Barry Elliott, Jamie Elliott

14th Edition

978-0273744443

Students also viewed these General Management questions