Question

1 Approved Answer

Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of

Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of completion is July 1, 2023. The building cost is estimated to be $20,000,000 and will be billed at $24,000,000. The following data relate to the construction period:

2020 2021 2022 2023
Cost to date 5,500,000 10,000,000 13,500,000 20,000,000
Estimated cost to complete 14,500,000 10,000,000 6,500,000 -0-
Progress billings to date 3,000,000 9,000,000 14,000,000 24,000,000
Cash collected to date 3,000,000 7,500,000 12,500,000 24,000,000

1) Compute the estimated gross profit for 2020, 2021, 2022, and 2023 assuming that the percentage-of-completion method is used.

2) Prepare the necessary journal entries for Chiefs Company for the years 2022 and 2023 under percentage-of-completion method.

3) Prepare the necessary journal entries for Chiefs Company for the years 2022 and 2023 under completed contract method.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Computer Accounting With QuickBooks Pro 2010

Authors: Donna UlmerDonna Kay

12th Edition

0077408756, 9780077408756

More Books

Students also viewed these Accounting questions

Question

Which Texas city has the most stores?

Answered: 1 week ago