Question
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of
Chiefs Construction Company has contracted to build an office building. The construction is scheduled to begin on January 1, 2020, and the estimated time of completion is July 1, 2023. The building cost is estimated to be $20,000,000 and will be billed at $24,000,000. The following data relate to the construction period:
2020 | 2021 | 2022 | 2023 | |
---|---|---|---|---|
Cost to date | 5,500,000 | 10,000,000 | 13,500,000 | 20,000,000 |
Estimated cost to complete | 14,500,000 | 10,000,000 | 6,500,000 | -0- |
Progress billings to date | 3,000,000 | 9,000,000 | 14,000,000 | 24,000,000 |
Cash collected to date | 3,000,000 | 7,500,000 | 12,500,000 | 24,000,000 |
1) Compute the estimated gross profit for 2020, 2021, 2022, and 2023 assuming that the percentage-of-completion method is used.
2) Prepare the necessary journal entries for Chiefs Company for the years 2022 and 2023 under percentage-of-completion method.
3) Prepare the necessary journal entries for Chiefs Company for the years 2022 and 2023 under completed contract method.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started