Q5. A very simple product {A} consists of a base (B) and a casting (C). The base consists of a plate (P)- and three fasteners

image text in transcribed
Q5. A very simple product {A} consists of a base (B) and a casting (C). The base consists of a plate (P)- and three fasteners (F). There are currently 30 castings and 100 bases on hand. Final assembly takes one week. The casting has a lead time of three weeks. All other parts have one week lead times. The MP5 requires 80 units of productA in Week 5, 120 in Week 8, and 90 in Week 10. Produce the MRP for the upcoming eight weeks. Produce a list of all planned order releases considering following additional information I There are currentlv 22 on hand of product A and it is expected to receive 25 in Week 4 and 30 in Week 7 from another manufacturing workshop - 40fasteners will arrive in Week 6 and 50 in Week 8 I 55 plates will arrive in Week 6 0 All components are lot for lot except for casting which can be ordered in batches of 25 (casting batch size is 25.)

Q5. A very simple product (A) consists of a base (B) and a casting (C). The base consists of a plate (P) and three fasteners (F). There are currently 30 castings and 100 bases on hand. Final assembly takes one week. The casting has a lead time of three weeks. All other parts have one week lead times. The MPS requires 80 units of product A in Week 5, 120 in Week 8, and 90 in Week 10. Produce the MRP for the upcoming eight weeks. Produce a list of all planned order releases considering following additional information There are currently 22 on hand of product A and it is expected to receive 25 in Week 4 and 30 in Week 7 from another manufacturing workshop 40 fasteners will arrive in Week 6 and 50 in Week 8 55 plates will arrive in Week 6 All components are lot for lot except for casting which can be ordered in batches of 25 (casting batch size is 25.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To solve this problem we need to create a material requirements plan MRP for the upcoming eight weeks for product A and its components Here is a stepb... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Statement Analysis

Authors: K. R. Subramanyam, John J. Wild

10th edition

73379433, 73379432, 978-0073379432

More Books

Students also viewed these Accounting questions

Question

List one of the facultys publications in APA style.

Answered: 1 week ago

Question

Make eye contact when talking and listening

Answered: 1 week ago

Question

Do not go, wait until I come

Answered: 1 week ago

Question

Pay him, do not wait until I sign

Answered: 1 week ago