Chrome's Jeans manufacturers blue jeans. They process the jeans in 40-jean batch sizes. The cutting time is 5 minutes per jean and the sewing time
Chrome's Jeans manufacturers blue jeans. They process the jeans in 40-jean batch sizes. The cutting time is 5 minutes per jean and the sewing time is 20 minutes per jean. It takes 2 minutes to move a batch from cutting to sewing. What is the total non-value-added time (in minutes) and the value added ratio, respectively? Round the ratio to one decimal place.
Step by Step Solution
There are 3 Steps involved in it
Step: 1