cindy's budget calls for 0.75 pond of butter per cake. cindy also budgeted to pay $2.40 pound of butter. the actual sales quantity for march
cindy's budget calls for 0.75 pond of butter per cake. cindy also budgeted to pay $2.40 pound of butter. the actual sales quantity for march is 4,000 cakes is 2,800 pounds.
what is the input quantity variance (i.e. materials efficiency variance) for the month of march