Question
1 Approved Answer
1.) (20 pts) Jobs arrive to a two-station serial line at a rate of 2 jobs per hour with deterministic inter- arrival times. Station
1.) (20 pts) Jobs arrive to a two-station serial line at a rate of 2 jobs per hour with deterministic inter- arrival times. Station 1 has one machine which requires exactly 29 minutes to process a job. Station 2 has one machine which requires exactly 26 minutes to process s job, provided it is up, but is subject to failures where the mean time to failure is 10 hours and the mean time to repair is 1 hour. SCV of repair is 1. a. (1 point) What is the SCV of arrivals to station 1? b. (1 point) What is the effective SCV of process times at station 1. c. (1 points) What is the utilization of station 1? d. (1 point) What is the cycle time in queue at station 1? e. (1 point) What is the total cycle time at station 1?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Lets solve each part of the question step by step Part a What is the SCV of arrivals to station 1 SCV stands for Squared Coefficient of Variation It is defined as the variance divided by the square of ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started