Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments

Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 1020 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture of the down payment. Occasionally, homes remain unsold for as long as three months after construction. In these situations, sales price reductions are used to promote the sale. During 2018, Citation began construction of an office building for Altamont Corporation. The total contract price is $15 million. Costs incurred, estimated costs to complete at year-end, billings, and cash collections for the life of the contract are as follows: 2018 2019 2020 Costs incurred during the year $ 3,000,000 $ 7,125,000 $ 3,375,000 Estimated costs to complete as of year-end 9,000,000 3,375,000 Billings during the year 1,500,000 7,500,000 6,000,000 Cash collections during the year 1,350,000 6,050,000 7,600,000 Also during 2018, Citation began a development consisting of 12 identical homes. Citation estimated that each home will sell for $720,000, but individual sales prices are negotiated with buyers. Deposits were received for eight of the homes, three of which were completed during 2018 and paid for in full for $720,000 each by the buyers. The completed homes cost $540,000 each to construct. The construction costs incurred during 2018 for the nine uncompleted homes totaled $3,240,000.

2018 2019 2020
costs incurred during the year 3,000,000 7,125,000 3,375,000
estimated costs to complete as of year-end 9,000,000 3,375,000 -0-
Billings during the year 1,500,000 7,500,000 6,000,000
cash collections during the year 1,350,000 6,050,000 7,600,000

Required:

1. Which method is most equivalent to recognizing revenue at the point of delivery?

2. Answer the following questions assuming that Citation uses the completed contract method for its office building contracts: 2-a. How much revenue related to this contract will Citation report in its 2018 and 2019 income statements? 2-b. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2018 and 2019? 2-c. What will Citation report in its December 31, 2018, balance sheet related to this contract? (Ignore cash.)

3. Answer the following questions assuming that Citation uses the percentage-of-completion method for its office building contracts. 3-a. How much revenue related to this contract will Citation report in its 2018 and 2019 income statements? 3-b. What is the amount of gross profit or loss to be recognized for the Altamont contract during 2018 and 2019? 3-c. What will Citation report in its December 31, 2018, balance sheet related to this contract? (Ignore cash.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Construction Contractors AICPA Audit And Accounting Guide

Authors: American Institute Of CPAs

1st Edition

0870519751, 978-0870519758

More Books

Students also viewed these Accounting questions

Question

The amount of work I am asked to do is reasonable.

Answered: 1 week ago

Question

The company encourages a balance between work and personal life.

Answered: 1 week ago