Civil Engineers team has one foremen costs $25.85/hr, one cement finisher costs $28.6/hr, five laborers cost $23.25/hr, and one equipment operator costs $31.45/hr. This team
Civil Engineers team has one foremen costs $25.85/hr, one cement finisher costs $28.6/hr, five laborers cost $23.25/hr, and one equipment operator costs $31.45/hr. This team can install 160 Cubic yards of concrete per eight hour a day.
A. Find the daily cost for the team.
B. Find the cost for the team per cubic yard of concrete.