Question

1 Approved Answer

Class work Depends Normal Crash Activity on Time Cost Time Cost A 6 days $700 4 days $800 B 4 days 400 4 days

image text in transcribed

Class work Depends Normal Crash Activity on Time Cost Time Cost A 6 days $700 4 days $800 B 4 days 400 4 days 400 C 5 days 650 5 days 700 D A 8 days 625 6 days 700 E B 10 days 200 9 days 350 F B 7 days 500 7 days 700 G C 3 days 600 3 days 600 H D, E 6 days 300 5 days 400 I F, G 7 days 350 6 days 425 Using the time-cost trade-off method a) how much you can compress this project to and what will be the total cost of the project? b) What is the optimal duration of the project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions