Clennon Production Company planned to use 1 yard of plastic per unit budgeted at $ 8 1 a yard. However, the plastic actually cost $

Clennon Production Company planned to use 1 yard of plastic per unit budgeted at $81 a yard. However, the plastic actually cost $80 per yard. The company actually made 3,900 units, although it had planned to make only 3,300 units. Total yards used for production were 3,960. How much is the total materials variance?
$3,960F
$900U
$4,860U
$48,600U
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting, Enhanced

Authors: Jerry J. Weygandt, Paul D. Kimmel, Donald E. Kieso

11th Edition

1119594596, 9781119594598

More Books

Students also viewed these Accounting questions