CO - 8 : Describe the activities involved with initiating and controlling production activities, including measuring performance, flow - shop scheduling, job - shop challenges,
CO: Describe the activities involved with initiating and controlling production activities, including measuring performance, flowshop scheduling, jobshop challenges, and machine scheduling.
Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job
Description
Predecessor
Expected time in days
A
Prepare preliminary sketches
NA
B
Outline specifications
NA
C
Prepare drawings
A
D
Write specifications
A B
E
Run prints
C D
F
Have specifications printed
B D
G
Assemble bid package
E F
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started