Company manufactures hockey sticks through two processes: Molding and Packaging. In the Molding department, the urethane, rubber, graphite, and other materials are molded into hockey
Company manufactures hockey sticks through two processes: Molding and Packaging. In the Molding department, the urethane, rubber, graphite, and other materials are molded into hockey sticks. In the Packaging department, the balls are placed in cartons and sent to the warehouse and stored as finished goods. All materials are entered at the beginning of each process. Labor and manufacturing overhead are incurred uniformly throughout each process. Production and cost data for the Molding department January 2019 are presented below.
Production Data | January |
Beginning work in process units | 0 |
Units started into production | 50,000 |
Ending Work in process units | 2,500 |
Percent complete ending inventory | 40% |
Cost Data |
|
Materials | $510,000 |
Labor | $92,500 |
Overhead | $150,000 |
Total | $752,500 |
Instructions
- Prepare a schedule showing physical units of production.
- Determine the equivalent units of production for materials and conversion costs.
- Compute the unit costs of production.
- Determine the costs to be assigned to the units transferred out and in process for January.
- Prepare a production cost report for the Molding Department for the month of January.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started