Question
Company manufactures soccer balls through a two-step process. First, the raw materials (polyurethane, rubber, polyester, and latex) are molded together in the Molding Department and
Company manufactures soccer balls through a two-step process. First, the raw materials (polyurethane, rubber, polyester, and latex) are molded together in the Molding Department and then are transferred to the Stitching Department to complete the manufacturing process. Company uses the First-In-First-Out method of Process Costing. Data relating to manufacturing activity in the Molding Department during the month of February is shown below:
Beginning Balance, Work in Process, (300 units, 60% complete) $3,000
Direct Materials (4,200 units started) 20,160
Direct Labor 8,400
Factory Overhead 16,495
Ending Balance, Work in Process (700 units, 30% complete) ?
In the Molding Department, materials are added at the beginning of the process and conversion costs are applied on a uniform basis.
Instructions
With respect to activity in the Molding Department for the month of February, using the 4 Ts calculate the following items. Show your work.
- The units in the BB WIP, Started and Completed, and EB WIP
- Calculate the equivalent units for direct materials and conversion costs.
- Calculate the cost per equivalent unit for direct materials and conversion costs.
- Calculate the cost of goods completed and transferred out (to the Stitching Department).
- Calculate the cost of the ending balance of Work in Process.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started