Company R s directors are planning to extend their factory. There is a risk that the site on which the extension will be built is
Company Rs directors are planning to extend their factory. There is a risk that the
site on which the extension will be built is structurally unsound. If it is then the cost
of building the extension will increase.
Company Rs board is considering addressing the risk by asking a building company
to agree to build the extension for a fixed price. Which of the following is the most
likely outcome of this approach?
A The building company will accept the risk of problems with the site.
B The building company will charge more to compensate for the risk.
C The building company will insist on building the extension elsewhere.
D The building company will seek damages from Company R if the site is
unsound.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started