Company Z is just starting to make a brand new product it has never made before. It has completed two units so far. The
Company Z is just starting to make a brand new product it has never made before. It has completed two units so far. The first unit took 19 hours to complete and the next unit took 15 hours. Based only on this information, what would be the estimate of the learning percentage in this process? Note: Round your answer to 1 decimal place. Estimated learning percentage