Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV =
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and with 50% of work completed $45,000.00 has been spent Calculate the following and submit the exercise results in a Word document. Budget at Completion (BAC) = #feet fence * cost/foot Planned Value (PV)- BAC * (%time passed) Earned Value (EV) BAC * % completed Actual Cost (AC) Cost Variance (CV) _EV - AC Schedule Variance (SV) EV - PV Cost Performance Index (CPI) . EVIAC % Schedule Performance Index (SPI) EV/PV % Estimate at Completion (EAC) BAC/CPI Estimate to Complete (ETC) EAC-AC Variance at Completion (VAC) BAC-EAC To Complete Performance Index _____ (BAC-EV)(BACIAC)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started