Question
Complete the following in Microsoft Project 2013 or later: Open the MS Project Assignment - Essay 4 Starting Point Download MS Project Assignment - Essay
Complete the following in Microsoft Project 2013 or later:
Open the MS Project Assignment - Essay 4 Starting Point Download MS Project Assignment - Essay 4 Starting Point and make the following changes:
Complete the following "Work" Resources and assign costs to them, as appropriate, to create a project budget (3 points)
John Smith
Beth Jones
Jennifer Williams
Mike Whitman
Joanna Edwards
Temporary Worker
Create the following "Material" Resources and assign costs to them, as appropriate, to create a project budget (3 points)
Concrete
Paint
Siding
Create the following "Cost" resources (3 points)
Permits
Inspection Fees
Contingency Reserve
Management Reserve
Define a "resource" calendar for Mike Whitman with a week of vacation during the project schedule (2 points)
Define Beth Jones to work only part-time (2 points)
Assign your work resources to tasks, ensuring that you have people working on each task that requires people. (10 points)
You may need to create more work resources so you do not have any that are overallocated. Feel free to add as many work resources as you deem necessary.
Resolve any resource overallocations (2 points)
Assign material resources to tasks, as appropriate. At a minimum, you must use a quantity greater than 1 of each material resource on at least one task. (2 points)
Assign cost resources to tasks, as appropriate. At a minimum, you must use each of your cost resources at a cost greater than $0 on at least one task. (2 points)
View your project budget (View the Gantt Chart Cost Table)
Verify the cost of all of your tasks.
Save your file with the Gantt Chart Cost Table visible - it must open to this sheet when I open it (1 point)
Gantt Chart Tools MS Project Assignment - Essay 4 Starting Point-1 - Project Professional File Task Resource Report Project View Help Format Tell me what you want to do do Cut Calibri - 12 Mark on Track Notes 0% 25% 50% 75% 100% Find - JOB Copy Respect Links Details Clear - Gant Paste BIUA Manually Auto Inspect Move Mode Task Summary Milestone Deliverable Information Scroll Chart Format Painter Inactivate Schedule Schedule Add to Timeline to Task Fill - View Clipboard Font Schedule Tasks Insert Properties Editing Sun 3/1/20 Jan 12, 20 Jan 19, '20 Jan 26, '20 Feb 2, 20 Feb 9, 20 Feb 16, '20 Feb 23, '20 Mar 1, 20 Mar 8, '20 Mar 15, '20 |Mar 22, 20 Mar 29, 20 TIMELINE Start Wed 1/8/20 Add tasks with dates to the timeline Qtr 2, 2020 Task Name Duration . Start Finish Predecessors . Deadline Resource Names - Add New Column Mar Apr May 21 3.3 Install windows, external doors 4 days Fri 3/6/20 Wed 3/11/20 20 NA 22 3.4 Install siding 3 days Thu 3/12/20 Mon 3/16/20 NA 23 3.5 Install roof 2 days Thu 3/12/20 Fri 3/13/20 22SS NA 3.6 External Work Completed 3/13 24 o days Fri 3/13/20 Fri 3/13/20 23 Fri 10/30/20 25 4 4 Distribute utilities 4 days Thu 3/12/20 Tue 3/17/20 NA 26 4.1 Distribute heating, cooling 2 days Mon 3/16/20 Tue 3/17/20 24 NA 27 4.2 Distribute electricity, phone, cabling 3 days Fri 3/13/20 Tue 3/17/20 26FF NA 28 4.3 Distribute water, sewer 4 days Thu 3/12/20 Tue 3/17/20 27FF NA 3/17 29 4.4 Distribute Utilities Completed 0 days Tue 3/17/20 Tue 3/17/20 28 Sun 11/1/20 30 4 5 Internal work 20 days Wed 3/18/20 Tue 4/14/20 NA 31 5.1 Frame internal walls 2 days Wed 3/18/20 Thu 3/19/20 29 NA 32 5.2 Install & finish drywall 3 days Fri 3/20/20 Tue 3/24/20 31 NA 33 5.3 Insulation 1 da Wed 3/25/20 Wed 3/25/20 32 NA 34 5.4 Paint 3 days Thu 3/26/20 Mon 3/30/20 33 NA GANTT CHART 5.5 Install flooring 3 days 3/31/20 Thu 4/2/20 NA 2 days Fri 4/3/20 Mon 4/6/20 35 NA 36 5.6 Install trim 37 5.7 Install built-in amenities 2 days Tue 4/7/20 Wed 4/8/20 36 NA 5 days Wed 4/8/20 Tue 4/14/20 37FS-50% NA 38 5.8 Install furnishings 4/14 days Tue 4/14/20 Tue 4/14/20 Fri 12/4/20 39 5.9 Internal Work Completed 38 4/14 39 Fri 12/4/20 6 Office Building Completed o days Tue 4/14/20 Tue 4/14/20Tools MS Project Assignment - Essay 4 Starting Point-1 - Project Professional Task Resource Report Project View Help Format Tell me what you want to do do Cu Calibri - 12 0% 25% 50% 75% 100% Mark on Track Copy + Notes Find - Paste Respect Links BIULA Inactivate Manually Auto Inspect Move Mode Details Format Painter Task Summary Milestone Deliverable Information - Clear Scroll Schedule Schedule Add to Timeline to Task Fill - Clipboard Font Schedule Tasks Insert Properties Jan 12, '20 Jan 19, '20 Jan 26, '20 Editing Feb 2, '20 Feb 9, '20 Start Feb 16, '20 Feb 23, '20 Mar 1, '20 Mar 8, '20 Mar 15, '20 Mar 22, '20 Mar 29, '20 Wed 1/8/20 Add tasks with dates to the timeline Half 1, 2020 Half 2, 2020 Half 1, 2021 Half 2, 2021 Task Name Duration - St Finish Predecessors - Deadline Resource Names AddN N M M N MM S N O My Construction 70 days Wed 1/8/20 Tue 4/14/20 NA 1 Pre-construction 12 days Wed 1/8/20 Thu 1/23/20 NA 1.1 Get approvals 1 day Wed 1/8/20 Wed 1/8/20 NA 1.2 Select architect 2 days Thu 1/9/20 Fri 1/10/20 NA 1.3 Draw plans 4 days Mon 1/13/20 Thu 1/16/20 NA 1.4 Review blueprints 2 days Fri 1/17/20 Mon 1/20/20 NA 1.5 Order materials 2 days Tue 1/21/20 Wed 1/22/20 NA 1.6 Building permit 1 day Thu 1/23/20 Thu 1/23/20 INA 1.7 Pre-construction completed 0 days Thu 1/23/20 Thu 1/23/20 Sat 9/12/20 1/23 4 2 Foundation 21 days Fri 1/24/20 Fri 2/21/20 NA 2.1 Survey and stake 2 days Fri 1/24/20 Mon 1/27/20 8 NA 11 2.2 Excavate for foundation 4 days Tue 1/28/20 Fri 1/31/20 10 NA 2.3 Footings 3 days Mon 2/3/20 Wed 2/5/20 11 NA 12 Thu 2/6/20 Fri 2/7/20 NA 13 2.4 Install drainage 2 days 12 Mon 2/10/20 Thu 2/13/20 13 NA 14 2.5 Install external utilities 4 days 2.6 Lay slab foundation Fri 2/14/20 Mon 2/17/20 15 2 days 14 NA NA 16 2.7 Foundation walls 2 days Thu 2/20/20 Fri 2/21/20 15FS+2 days 16 2.8 Foundation Completed o days Fri 2/21/20 Fri 2/21/20 Fri 10/9/20 17 16 days Mon 2/24/20 Mon 3/16/20 NA 18 4 3 External work 19 3.1 Erect steel frame 4 days Mon 2/24/20 Thu 2/27/20 17 NA 20 3.2 Erect external walls 5 days Fri 2/28/20 Thu 3/5/20 20 NA 3.3 Install windows, external doors 4 days Fri 3/6/20 Wed 3/11/20 21 NA Thu 3/12/20 Mon 3/16/20 21 22 3.4 Install siding 3 days Thu 3/12/20 Fri 3/13/20 22SS NA 23 3.5 Install roof 2 days Fri 10/30/20 3.6 External Work Completed o days Fri 3/13/20 Fri 3/13/20 23 24 NA Thu 3/12/20 Tue 3/17/20 25 4 4 Distribute utilities 4 days NA 4.1 Distribute heating, cooling 2 days Mon 3/16/20 Tue 3/17/20 24 26 Fri 3/13/20 Tue 3/17/20 26FF NA 27 4.2 Distribute electricity, phone, cabling 3 days 27FF NA 4 days Thu 3/12/20 Tue 3/17/20 28 4.3 Distribute water, sewer 3/17 Tue 3/17/20 Tue 3/17/20 28 Sun 11/1/20 29 4.4 Distribute Utilities Completed o days Ready New Tasks : Auto ScheduledStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started